Nevsun Drills 37.5m of 8.26% Copper Adjacent to Bisha Mine

27.10.2011  |  Marketwired

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 10/27/11 -- Nevsun Resources Ltd. (TSX: NSU)(NYSE Amex: NSU) is pleased to report the assays from the final four diamond drill holes from the hanging wall copper phase one drilling at the Bisha Deposit. These four holes were delayed due to mining operations in the area.


Highlights



-- Extension of Bisha Main Sulphide Lens
-- Near surface copper mineralization adjacent to Bisha Main deposit
-- Likely additional feed for Bisha supergene copper phase


Select High Grade Results Include:



-- Hole B-464 - 37.5m at 8.26% Cu, from 31.5 meters to 69.0 meters
-- Hole B-465 - 12.0m at 1.29% Cu, from 76.0 meters to 88.0 meters


Drill holes B-464 and B-465 intersected the same supergene sulphide lens that was intersected by drill hole B-395 and B-396 that were previously reported in the press release issued August 31, 2011. Drill hole spacing is approximately 50m x 50m. The sulphide lens appears to be an extension of the northwest lens of Bisha that was faulted off and is not included in currently disclosed resources.


Detailed results are in the following table together with a map of the hole locations.



----------------------------------------------------------------------------
From To Interval Au Ag Cu Zn
Hole ID (m) (m) (m) (ppm) (ppm) (%) (%) Azimuth Dip Zone
----------------------------------------------------------------------------
B-463 49.50 61.50 12.00 0.01 1.00 0.79 0.02 270 -45 HW Cu
incl. 58.50 61.50 3.00 0.01 1.00 1.54 0.02 HW Cu
----------------------------------------------------------------------------
B-464 31.50 69.00 37.50 0.58 32.27 8.26 0.10 270 -90 Supg
Incl. 40.50 51.00 10.50 0.98 70.14 16.99 0.04 Supg
and 58.10 61.80 3.70 1.16 70.00 26.50 0.23 Supg
----------------------------------------------------------------------------
B-465 45.00 64.00 19.00 0.04 1.95 0.58 0.02 270 -45 HW Cu
Incl. 57.50 64.00 6.50 0.09 3.77 1.12 0.02 HW Cu
And 76.00 88.00 12.00 0.56 16.75 1.29 0.01 Supg
----------------------------------------------------------------------------
B-466 43.50 109.50 66.00 0.01 1.07 0.50 0.03 270 -45 HW Cu
Incl. 43.50 46.50 3.00 0.01 2.50 2.28 0.01 HW Cu
and 81.00 84.00 3.00 0.01 1.00 1.48 0.03 HW Cu
----------------------------------------------------------------------------
Note: True thickness is estimated at approximately 90% of the drill
intervals reported in the table.


Phase II drilling of the hanging wall copper zone, designed to further infill drill the zone as well as the newly identified lens is complete and assay results are expected later in Q4.


The Company also completed a 16,000 meter diamond drill program on the Bisha Main deposit below the existing planned pit. Final results of this drill program are expected soon with a second resource and reserve re-statement now targeted for Q1 2012. Nevsun had previously guided Q4 2011 but has pushed back the date due to additional drilling follow-up on the above and availability of third party engineers.


Darin Wasylik, Senior Geologist for Nevsun, a qualified person under National Instrument 43-101, supervised and directed all work associated with the drilling program.


Sample preparation and analysis were conducted at ALS Chemex of Vancouver, Canada.


Forward Looking Statements: The above contains statements regarding positive drill results, near term additional drill results and anticipated resource and reserve re-statement. Forward-looking statements are frequently, but not always, identified by words such as 'expects', 'anticipates','believes', 'intends', 'estimated', 'potential', 'possible' and similar expressions, or statements that events, conditions or results 'will', 'may', 'could' or 'should' occur or be achieved. Forward-looking statements are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors, including, without limitation, those described in the Management Discussion and Analysis of the Company. The Company's forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made and the Company assumes no obligation to update such forward-looking statements in the future. For the reasons set forth above, investors should not place undue reliance on forward-looking statements.


NEVSUN RESOURCES LTD.


Cliff T. Davis, President & Chief Executive Officer


To view the Map associated with this release, please visit the following link: http://media3.marketwire.com/docs/nsu27_F1.pdf

Contacts:

Kin Communications

604-684-6730 or Toll Free: 1-866-684-6730
ir@kincommunications.com
www.nevsun.com



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Nevsun Resources Ltd.
Bergbau
-
-
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"