Suche
 
Folgen Sie uns auf:

Kipoi Stage 2 Sxew construction update

09.04.2013  |  CNW

/NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES/

PERTH, Western Australia, April 9, 2013 /CNW/ - Tiger Resources Limited (ASX/TSX: TGS, "Tiger") is pleased to provide an update on construction of the Stage 2 Solvent Extraction Electro-Winning (SXEW) plant at the Kipoi Copper Project in the Democratic Republic of Congo (DRC).

Project construction of the SXEW commenced on 16 January 2013 and is on schedule for first production of copper cathode in mid-2014.

Site Works and Construction

Progress with site works and civils is progressing well, with more than 60% of the bulk earthworks completed. A 70-man construction camp has been erected, and permanent site accommodation units are close to completion. Civil works for the laydown area are completed and are awaiting fencing.  The pad area for a 5 MVA electrical substation is completed.

Lump sum turnkey (LSTK) contracts have been executed with the principal contractor Senet Pty Ltd (SENET) for the supply of the SXEW plant, agglomerator and stacking conveyer system. Additional fixed-price contracts have been executed for the accommodation facilities, power supply and reticulation and earthworks, and for the supply and installation of the heap leach pads.

LSTK and fixed priced contracts have now been executed for works totalling $110 million of the $161 million project budget. The balance of the project budget cost is allocated to owner's and project management costs ($21 million including taxes, duties and fees), with the remainder of $30 million provided as an unallocated contingency.

SENET is currently ahead of schedule with the design and fabrication of the plant, with all design layout work complete and more than 190 tonnes of steel fabricated.

Financing

The necessary documentation and approvals process for the $80 million ECIC standby term loan facility are progressing well. Site visits have been undertaken by the mandated arranging banks, Nedbank Capital and Rand Merchant Bank, and by the nominated Independent Technical Expert. Execution of the $30 million facility which is to be made available by Nedbank Capital and Rand Merchant Bank in advance of the ECIC standby term facility is progressing with legal negotiations on the facility agreements currently in progress.  The facility remains subject to the lender's credit committee approvals, with first drawdown immediately available after the satisfaction of customary conditions precedent.

Stage 1 HMS Operations

The Stage 1 heavy media separation (HMS) plant at Kipoi continues to generate the cash flow required to meet the SXEW capital expenditure, with March 2013 delivering a new monthly production record of 4,007t of copper, 37% above nameplate capacity. Production for the March 2013 quarter of 9,488 tonnes of copper in concentrate exceeded guidance by 3%.

The full copy of the announcement is available in a release that has been filed with SEDAR and is posted on the Company's website at www.tigerresources.com.au

SOURCE Tiger Resources Limited

For further information in respect of the Company's activities, please contact:

Brad Marwood 
Managing Director 
(+61 8) 6188 2000  
bmarwood@tigerez.com

Stephen Hills 
Chief Financial Officer
 (+61 8) 6188 2000
 shills@tigerez.com

Nathan Ryan
 Investor Relations  
(+61 0) 420 582 887
 nryan@tigerez.com

Company website: www.tigerresources.com.au


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Tiger Resources Ltd.
Bergbau
A0CAJF
AU000000TGS2
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"