Suche
 
Folgen Sie uns auf:

Tintina Resources Reports Pre-Tax 30.5% IRR and $218M NPV for Updated Preliminary Economic Assessment, Black Butte Copper Project, Montana, USA

25.06.2013  |  Marketwired

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 06/24/13 -- Tintina Resources Inc. ("Tintina" or the "Company") (TSX VENTURE: TAU)(OTCQX: TINTF) is pleased to announce the positive results of an updated Preliminary Economic Assessment (the "Updated PEA") for its 100% owned Black Butte Copper Project (the "Project") located in central Montana, USA. All currency amounts are in United States dollars (US$) unless stated otherwise. The pre-tax results include: an internal rate of return ("IRR") of 30.5%, a net present value ("NPV") of $218M at an 8% discount rate, and a payback of 3.6 years using an assumed life of mine copper price of $3.05. Once in operation, the Black Butte Copper Project would provide approximately 200 jobs per year during the 11 year mine life. All of the currently known resources and mine-related site facilities for the Black Butte property discussed in the Updated PEA are on private ranch lands (see Figures 1 and 2).


The Company commissioned the Updated PEA to supplant the Company's previously filed PEA dated August 30, 2012. The Updated PEA incorporates the results of recent diamond drilling on the Johnny Lee Deposit and a revised sequence of mining based on the updated resource estimate disclosed in the Company's press release dated November 13, 2012. The Updated PEA does not include the Lowry deposit.


Please note that the Updated PEA is preliminary in nature, that it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and that there is no certainty that the Updated PEA will be realized. Please see the important disclosure under "Cautionary Note Regarding the Updated PEA" below.


HIGHLIGHTS



-- Initial estimated startup capital of $217.8 million including a 22%
contingency of $33.3 million. Estimated sustaining capital is $114.7
million over an 11 year mine life
-- Base case using long-term copper price of $3.05 / pound (lb)(i)
-- Pre-tax NPV of $218 million at an 8% discount rate with an IRR of
30.5% and 3.6 year payback
-- Post-tax NPV of $110 million at an 8% discount rate with an IRR of
20.2% and 4.7 year payback(ii)
-- Underground mining operation with 11-year mine life at a nominal
processing rate of 3,300 tonnes (t) per day using a conventional
flotation circuit producing a single copper concentrate
-- Average annual payable metal production estimated at 62.06 million
pounds of copper
-- Life-of-mine payable metal production estimated at 682.62 million pounds
of copper
-- Operating cost $66.48/t milled; cash cost $1.81/lb copper (including
royalty)
-- The Life of Mine copper recovery is estimated to average 88.3%

(i) $3.05/lb copper price is based on the Energy and Metals Consensus
Forecast's (EMCF) Mean price as of April 26, 2013 (the "EMCF Price"). The
EMCF Price is a forward looking consensus of metal prices among 20 leading
international financial institutions and is published by Consensus
Economics, UK.
(ii) Post-tax economic values were calculated by applying the following
taxes based on enacted tax law and regulations as of June 10, 2013: United
States Federal corporate income taxes, Montana State income taxes, Montana
metalliferous mines license taxes, and Montana mines gross proceeds taxes.
The calculation of post-tax economic values did not account for loss carry
forwards and unutilized tax pools which would be expected to reduce actual
taxes payable.


Rick Van Nieuwenhuyse, Executive Chairman of Tintina, stated, "The Company is very pleased with the results of the Updated PEA. The recent in-fill drilling resulted in significantly improved grades in the Johnny Lee deposit and allowed for better mine scheduling which significantly improved the overall project economics."


Jerry Zieg, Vice President of Exploration for Tintina, added, "The Updated PEA results certainly support advancing the project. Management believes that the Black Butte Copper Project is one of the most significant North American copper development stories around today. In addition, our geologic work continues to show that the district has a considerable exploration upside."



Table 1: Resources used in study
----------------------------------------------------------------------------
Undiluted Measured Mineral Resources(1)- Johnny Lee Deposit
----------------------------------------------------------------------------
Tonnes Estimated
(in millions) Cu Grade (%)
----------------------------------------------------------------------------
Johnny Lee Upper Zone 2.66 2.99
----------------------------------------------------------------------------
Undiluted Indicated Mineral Resources(1)- Johnny Lee Deposit
----------------------------------------------------------------------------
Johnny Lee Upper Zone 6.52 2.77
----------------------------------------------------------------------------
Johnny Lee Lower Zone 2.39 6.40
----------------------------------------------------------------------------
TOTAL UNDILUTED MEASURED AND INDICATED
MINERAL RESOURCE(1) 11.57 3.57
----------------------------------------------------------------------------
Undiluted Inferred Mineral Resources(1)- Johnny Lee Deposit
----------------------------------------------------------------------------
Johnny Lee Upper Zone 1.25 2.52
----------------------------------------------------------------------------
Johnny Lee Lower Zone 0.21 5.33
----------------------------------------------------------------------------
(1) Mineral Resource estimates for the Johnny Lee Upper and Lower zones were
prepared by Mike Lechner P. Geo., President of Resource Modeling Inc., who
is an independent Qualified Person as defined by NI 43-101. The effective
date of the resource estimates is November 13, 2012. The drill hole database
that was used to estimate Mineral Resources consists of 106 drill holes
totaling 23,705 meters for the Johnny Lee Upper Zone and 47 drill holes
totaling 21,783 meters for the Johnny Lee Lower Zone.
Mineral resources that are not mineral reserves do not have demonstrated
economic viability. Mineral Resource estimates were completed for each zone
by constructing three dimensional computer block models with block sizes of
5 m x 5 m in the X and Y dimensions and 1 m in the Z dimension. Three-
dimensional wireframes were constructed representing the Johnny Lee Upper
and Lower copper zones using logged massive sulfide lithologies and a
nominal copper cutoff grade of 1%. One-meter-long drill hole composites were
generated from the assay data after capping high-grade outliners and were
subsequently used to estimate copper, cobalt, gold, and silver grades using
a dynamic anisotropy search strategy and an inverse distance weighting
estimator. The block grades were validated visually and by comparing the
inverse distance grades with a nearest neighbor model.


JOHNNY LEE DEPOSIT UPDATED PRELIMINARY ECONOMIC ASSESSMENT OVERVIEW



Table 2: Johnny Lee Mine Metrics(1)
----------------------------------------------------------------------------
Mill Feed(2) 11.84 M tonnes(1)
----------------------------------------------------------------------------
Average Copper Grade 3.11%(1)
----------------------------------------------------------------------------
Total Dry Concentrate Production 1.38 M tonnes
----------------------------------------------------------------------------
Average Annual Payable Copper Production 62.06 M pounds
----------------------------------------------------------------------------
Life of Mine Payable Copper Production 682.62 M pounds
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Mine Operating Cost $45.83/tonne
----------------------------------------------------------------------------
Mill Operating Cost $15.83/tonne
----------------------------------------------------------------------------
G&A, Surface Services, and Tailings Management $4.82/tonne
----------------------------------------------------------------------------
Total Site Operating Cost $66.48/tonne
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Direct Capital Costs(3) $152.2 M
----------------------------------------------------------------------------
Indirect and Owners(3) $32.2 M
----------------------------------------------------------------------------
Contingency(3) $33.3 M
----------------------------------------------------------------------------
Total Pre Production Capital Costs(3,4) $217.8 M
----------------------------------------------------------------------------
Total Sustaining Capital(4) $114.7 M
----------------------------------------------------------------------------
(1) Figures reflect assumed mine dilution and mine recovery factors.
(2) Mill feed includes Measured, Indicated, and Inferred mined material.
(3) Total Pre-Production Capital Costs may not add due to rounding.
(4) Estimate considered accurate to +40% and -40%.


PROJECT ECONOMICS


The table below highlights the pre-tax IRR and NPV at an 8% discount for a selection of copper prices.



Table 3: Economic Sensitivity Summary(1)
----------------------------------------------------------------------------
Pre-Tax NPV Pre-Tax Post-Tax NPV Post-Tax
Copper Pre-Tax @ 8% Payback Post-Tax @ 8% Payback
Price ($) IRR (%) (in millions $) (Years) IRR(%) (in millions $) (Years)
----------------------------------------------------------------------------
2.50 11.3 28 6.2 5.5 -21 8.3
----------------------------------------------------------------------------
3.05 30.5 218 3.6 20.2 110 4.7
----------------------------------------------------------------------------
3.50 44.7 373 2.8 30.4 210 3.6
----------------------------------------------------------------------------
(1) Post-tax economic values were calculated by applying the following taxes
based on enacted tax law and regulations as of June 10, 2013: United States
Federal corporate income taxes, Montana State income taxes, Montana
metalliferous mines license taxes, and Montana mines gross proceeds taxes.
The calculation of post-tax economic values did not account for loss carry
forwards and unutilized tax pools which would be expected to reduce actual
taxes payable.


UPDATED PEA CONTRIBUTIONS AND QUALIFIED PERSONS


The Updated PEA and resource estimates have been prepared in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument (NI) 43-101 of the Canadian Securities Administrators. The technical contents of this release and all technical information relating to the Updated PEA have been reviewed and approved by Srikant Annavarapu, P.Eng. (AMEC), Art Winckers, P.Eng. (Arthur H. Winckers and Associates Inc.), Mike Lechner, P.Geo. (Resource Modeling Inc.), Wayne Stoyko, P.Eng. (Tetra Tech), and Jianhui Huang, P.Eng. (Tetra Tech), the Qualified Persons responsible for preparation of the Updated PEA, each of whom have verified the technical data, qualifications, and assumptions in this release and are independent of Tintina. Readers are encouraged to read the Updated PEA Technical Report in its entirety when it is filed under the Company's profile on SEDAR at www.sedar.com.


Jerry Zieg, Vice President of Exploration for the Company, is a Qualified Person for the purposes of NI 43-101 and has also reviewed and approved the information of a scientific or technical nature contained in this news release. Assays for this program have been completed by ALS Chemex including duplicates, standards, and blanks for QA/QC purposes.


ABOUT TINTINA RESOURCES INC.


Tintina Resources Inc. is a growth company focused on the exploration and development of base metal properties in North America. The Company's experienced Board of Directors and Management Team is currently focused on advancing the Black Butte Copper Project located in central Montana towards a production decision.


ON BEHALF OF THE BOARD OF DIRECTORS


GERALD BOOTH, Interim CEO


Cautionary Note Regarding the Updated PEA: The Updated PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Furthermore, there is no certainty that the preliminary economic assessment will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Readers are encouraged to read the technical report when it is filed.


Cautionary Note Regarding Forward-Looking Statements: Certain disclosures in this release, including statements regarding the Company's plans for and intentions with respect to exploration and development of the Company's Black Butte Copper Project and the results thereof, resource estimates, the Updated PEA, including estimates of capital and sustaining costs, anticipated internal rates of return, mine production, estimated recoveries, mine life, estimated payback period and net present values, the preparation of a feasibility study and other plans and objectives of the Company with respect to the Black Butte Project and surrounding area constitute "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and Canadian securities legislation. In making the forward-looking statements in this release, the Company has applied certain factors and assumptions that the Company believes are reasonable, including that the Company is able to obtain any government or other regulatory approvals and any financing required to complete the Company's planned exploration and development activities, that the Company is able to procure equipment and supplies in sufficient quantities and on a timely basis, that the Company's exploration and development activities on the Black Butte Copper Project will not be affected by actions of environmental activists or other special interest groups, that actual results of exploration activities are consistent with management's expectations, that the proposed mine plan and recoveries will be achieved, that capital costs and sustaining costs will be as estimated, that the assumptions underlying mineral resource estimates are valid and that no unforeseen accident, fire, ground instability, flooding, labor disruption, equipment failure, metallurgical, environmental or other events that could delay or increase the cost of development will occur. However, the forward-looking statements in this release are subject to numerous risks, uncertainties and other factors relating to Tintina's operation as a mineral exploration and development company and the Black Butte Copper Project that may cause future results to differ materially from those expressed or implied in such forward-looking statements.


Such uncertainties and risks include, among others, actual results of the Company's exploration activities being different than those expected by management, uncertainties involved in the interpretation of drilling results and geological tests, delays in obtaining or inability to obtain required government or other regulatory approvals or financing, interference with Tintina's exploration or development activities by environmental activists or other special interest groups, inability to procure equipment and supplies in sufficient quantities and on a timely basis, the risk of unexpected variations in mineral resources, grade or recovery rates, of failure of plant, equipment or processes to operate as anticipated, of accidents, labor disputes, and unanticipated delays in obtaining governmental approvals and completing other development activities, the risk that estimated costs will be higher than anticipated and the risk that the proposed mine plan and recoveries will not be achieved, equipment breakdowns and bad weather. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Readers are cautioned not to place undue reliance on forward-looking statements. Tintina does not intend, and expressly disclaims any intention or obligation to, update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by law.


To view Figures 1 and 2, please visit the following link: http://media3.marketwire.com/docs/tau624i.pdf.


Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:

Tintina Resources Inc.

Tiffany Konings

(604) 628-1162

(604) 628-1163 (FAX)
info@tintinaresources.com
www.tintinaresources.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Sandfire Resources America Inc.
Bergbau
A2JSFH
CA8000281029
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"