Suche
 
Folgen Sie uns auf:

Atna Provides Technical Report Results for the Pinson Underground and Mag Open Pit Projects

15.09.2014  |  CNW

GOLDEN, Colo., Sept. 15, 2014 /CNW/ -- Atna Resources Ltd. ("Atna" or the "Company") (TSX:ATN / OTCQB:ATNAF) is pleased to present the results of its Technical Report that provides an updated resource estimate and mine plan for its Pinson Underground Project and the results of a positive pre-feasibility study for the Mag Open Pit Project at Pinson. Pinson is located in Humboldt County, Nevada. 

"Both projects, the Pinson Underground and the Mag Open Pit demonstrate positive economic results that will withstand downside pressures in gold price and increased capital and operating costs. The technical report supports increasing the rate of production at Pinson Underground where mining began three months ago. The study also demonstrates that the Mag Open Pit project is economically attractive and provides the basis to commence the permitting process. The combined Pinson Underground and Mag Open Pit operations have the potential to return over $100 million in cash flow to shareholders at cash costs estimated to be on the order of $700 per ounce. The study focused on maximizing the extraction of well defined reserves and resources. Significant additional potential remains to convert resources to mineral reserves and to generate economic synergies between the two projects," states James Hesketh, President & CEO.  

Pinson Underground Summary

  • Criteria and grade shells used to develop the mineral resource model reflect tighter grade shell constraints and reduced projections along strike and down dip to reflect experience gained during the mining campaign of 2012 to 2013.
  • Proven and Probable reserves contain 160,000 ounces at a grade of 0.403 oz/ton
  • 4 year mine life with upside: a high resource to reserve conversion potential with infill drilling
  • Mining methods: Long hole stoping with delayed fill and underhand drift and fill
  • Gold Production: 30,000 to 45,000 ounces per year
  • Average cash cost: $658/oz; Average full cost: $767/oz
  • Sustaining capital: $14.3 million over 4 years
  • Pre-tax NPV @ 8% discount: $61 million at $1,300 Au
  • Project economics remain positive over a wide range of operating costs, capital costs and gold prices.

Mag Open Pit Summary

  • Constrained to private land section only, which contains approximately 50% of resource base
  • Conventional open pit, crush, heap leach operation
  • Total 183,600 gold ounces recovered over 6-year life
  • Pre-tax NPV @ 8% discount: $28.1 million; IRR=19.5%
  • Total CAPEX: $66.9 million including mining equipment, crushing plant and ADR gold recovery plant
  • Upsides: Contract mining vs. self mine; ROM leach vs. crush leach  

A number of reputable firms and their Qualified Persons worked on the study, which will be released in an NI43-101 compliant Technical Report. Golder Associates Inc. (Golder) of Lakewood, Colorado was the primary author of the report and was responsible for open pit and heap leach design and costing and takes overall responsibility for its content except as noted below. SGS-Metcon/KD Engineering of Tucson, Arizona were responsible for open pit metallurgy, crushing and recovery plant designs and for the cost estimates of those facilities. Open pit resources were estimated by Gustavson Associates of Lakewood Colorado. Practical Mining of Elko, Nevada completed underground resources, mine plans and economic costing.  The Technical Report will be filed following this press release. All units in this release are in English or Imperial units and all costs are in US dollars.  Federal income taxes for the projects were each estimated on a project stand-alone basis using statutory tax rates and do not take into account previous losses, acquisition costs, or the effect of corporate consolidation and overheads and may overstate actual tax impacts. 

This press release was prepared under the supervision and review of William Stanley, V.P. Exploration of Atna, a Registered Member of the Society for Mining, Metallurgy, and Exploration (No. 3069054), a Licensed Geologist and qualified person, as defined in NI 43-101, who has verified the authenticity and validity of the technical information contained within this news release.

Pinson Underground

Practical Mining LLC of Elko, Nevada was retained to compile a new resource model and mine design for the Pinson Underground project based on all drill results and experience gained from previous mining and development carried out by Atna to date. The previous mining experience at Pinson was used to update the underground resource estimate and increase the confidence in using the estimate for production mine design. The criteria and grade shells used to develop the mineral resource model were modified to reflect the extent of mineralization encountered during the mining campaign of 2012 to 2013. The Pinson Mine underground resources are summarized in the tables below. The CX resources within section 32 include only Atna's 41.66% ownership interest.

Pinson Mine Underground Mineral Resources by Area



Measured

Indicated

Measured + Indicated

Inferred

Redox

Area

ktons

opt

koz

ktons

opt

koz

ktons

opt

koz

ktons

opt

koz

Oxide

CX Section 32

0.3

0.449

0.1

24.6

0.360

8.9

25.0

0.361

9.0

49.1

0.346

17.0

CX Excluding Section 32

0.0

0.000

0.0

98.8

0.317

31.3

98.8

0.317

31.3

192.5

0.297

57.2

CX West

3.2

0.366

1.2

67.2

0.342

23.0

70.4

0.343

24.2

16.7

0.288

4.8

Line Hole North

0.0

0.000

0.0

0.0

0.000

0.0

0.0

0.000

0.0

6.8

0.463

3.2

Line Hole South

6.0

0.374

2.3

4.1

0.399

1.6

10.1

0.384

3.9

0.0

0.000

0.0

Ogee

19.9

0.515

10.3

46.6

0.478

22.3

66.5

0.489

32.5

13.1

0.314

4.1

Otto

1.3

0.352

0.5

3.8

0.302

1.2

5.2

0.315

1.6

1.5

0.310

0.5

Range Front

0.0

0.000

0.0

0.0

0.000

0.0

0.0

0.000

0.0

86.6

0.631

54.7

Subtotal Oxide

30.8

0.464

14.3

245.1

0.360

88.2

275.9

0.372

102.5

366.2

0.386

141.4

Sulfide

Adams Peak

4.2

0.338

1.4

67.9

0.380

25.8

72.1

0.378

27.2

43.6

0.395

17.2

CX Section 32

0.0

0.000

0.0

10.9

0.507

5.5

11.0

0.506

5.6

15.9

0.465

7.4

CX Excluding Section 32

0.0

0.000

0.0

20.6

0.340

7.0

20.7

0.340

7.0

232.6

0.344

79.9

CX West

2.1

0.545

1.1

54.4

0.320

17.4

56.5

0.329

18.6

38.1

0.430

16.4

Line Hole North

0.0

0.000

0.0

10.4

0.472

4.9

10.4

0.472

4.9

231.1

0.520

120.1

Line Hole South

3.8

0.632

2.4

1.3

0.631

0.8

5.0

0.632

3.2

0.0

0.000

0.0

Ogee

24.6

0.697

17.1

90.1

0.619

55.7

114.7

0.635

72.9

297.0

0.491

145.8

Otto

4.3

0.351

1.5

83.2

0.493

41.0

87.5

0.486

42.5

69.8

0.457

31.9

Range Front

0.0

0.000

0.0

152.9

0.409

62.6

152.9

0.409

62.6

377.7

0.372

140.5

Subtotal Sulfide

39.0

0.605

23.6

491.7

0.449

220.8

530.7

0.461

244.4

1,305.7

0.428

559.3

Total

67.7

0.543

37.9

736.9

0.419

309.1

806.6

0.43

346.9

1,671.9

0.419

700.7

Both the underground mineral resources and underground proven and probable reserves disclosed, described and evaluated in the May 18, 2012 Technical Report on the property, are not deemed current by Atna and have been updated in this Technical Report to reflect tighter grade shell constraints and reduced projections along strike and down-dip from previous estimates. Pinson Underground mineral resources were estimated using cut-off grades of 0.22 opt and 0.19 opt for oxide and refractory sulfide mineral resources respectively calculated using a $1,500 gold price. Work completed during underground development operations in 2012 and 2013 provided significant insight into the appropriate mining methods and ground conditions present at the project.

Pinson Underground Mineral Reserves


Proven

Probable

Proven + Probable

Area

ktons

Opt

koz.

ktons

opt

koz.

ktons

opt

koz.

Adams Peak

4.4

0.230

1.0

52

0.353

18

56

0.344

19

CX West

2.8

0.233

0.7

4.7

0.348

1.6

7.5

0.305

2.3

Linehole South

7.4

0.357

2.6

2.3

0.399

0.9

9.6

0.367

3.5

Ogee

48

0.443

21

103

0.480

50

151

0.468

71

Otto

7.5

0.187

1.4

70

0.399

28

77

0.379

29

Range Front




95

0.367

35

95

0.367

35

Total

70

0.384

27

327

0.408

133

397

0.403

160

Note: Oxide and sulfide mineral reserves have been estimated at a cutoff grades of 0.23 opt and 0.22 OPT respectively using a gold price of $1,300 per ounce. Mineral Reserves include allowances for 5% mining losses and 10% unplanned dilution at zero grade.

Underground mining at Pinson consists of two primary mining methods: long-hole open stoping with delayed backfill and underhand drift and fill.  The preferred sequence for long-hole stopes is to mine from the bottom up and for drift and fill to mine underhand or from the top down.  Previous mining at Pinson was exclusively underhand drift and fill. The mine plan assumes a two-crew operation in the fourth quarter of 2014 expanding thereafter to a maximum mining rate of 520 tons per day in 2016. Forecast production declines in 2017 with the depletion of known proven and probable reserves. Additional infill and step-out drilling from the underground workings will be required to convert additional resources to reserves and extend mine life. The four-year mine plan is shown in the following table:


2014

2015

2016

2017

Total

Oxide Ore Mined (ktons)

13

23

48

27

110

Grade (opt)

0.290

0.156

0.238

0.263

0.233

Contained Gold (koz.)

3.6

3.5

11.5

7.1

25.7







Refractory Ore Mined (ktons)

9

103

142

33

287

Grade (opt)

0.696

0.431

0.471

0.510

0.468

Contained Gold (koz.)

6.1

44.4

67.0

17.0

134.4







Total Ore Mined (ktons)

21

126

190

60

397

Grade (opt)

0.457

0.381

0.412

0.399

0.403

Contained Gold (koz.)

9.7

47.9

78.5

24.0

160.1







Gold Sales (koz.)

7.7

40.0

64.8

18.9

131.5







Stope Development Drift Ore (ktons)

9

60

64

8

141

Mechanized Stope Ore Mined (ktons)

12

65

121

52

251

Shrink Stope Ore Mined (ktons)

-

-

6

-

6







Expensed Waste Mined (ktons)

1

30

25

10

65







Primary Development Drifting (feet)

-

3,267

3,179

236

6,682

Secondary Development Drifting (feet)

-

1,053

547

40

1,640

Raise Development (feet)

-

247

142

186

575

Production at the Pinson Underground mine commenced in June 2014. The required infrastructure necessary to support the planned level of underground mining is currently in place and previous mining has provided insight into the ground conditions and the appropriate mining methods for extraction of the mineral reserves. A contract with a qualified underground mining contractor is in place and a number of lots of oxide and refractory mineralized material mined underground have been sold to third-party processing facilities with favorable results. Mine capital and risk exposure has been minimized by using a contractor. Future capital spending is limited to 6,700 feet of mine development to access reserves below the current extent of mine development at the 4600 level and above the 4100 planned lowest level. These factors provide a strong basis for the capital and operating costs used in the study.  

Economic analysis of the Pinson underground project, at a gold price of $1,300 per ounce, shows a net pre-tax Net Present Value (NPV) at an 8% discount rate of $61 million. The after-tax NPV at an 8% discount rate is $51.7 million. These results are estimated on a stand-alone basis with no operating synergies being considered in combination with the Mag Open Pit.

Calendar Year

 Total

2014

2015

2016

2017







Pinson Underground

Income Statement ($ 000's)












Total Gold Sales (ounces)

170,971

10,051

52,039

84,253

24,628







Total Operating Cost

(71,922)

(4,045)

(23,464)

(33,261)

(11,152)

Royalty

(10,258)

(603)

(3,122)

(5,055)

(1,478)

Nevada Net Proceeds Tax

(4,352)

(270)

(1,254)

(2,263)

(564)

Total Cash Cost

(86,532)

(4,918)

(27,841)

(40,579)

(13,194)

EBITDA

84,439

5,133

24,198

43,673

11,434







Depreciation

(14,340)

0

(2,351)

(8,582)

(3,407)

Pre-Tax Income

70,099

5,133

21,847

35,091

8,027

Income Tax

(18,375)

(1,339)

(7,288)

(8,124)

(1,624)







Net Income

51,724

3,795

14,559

26,967

6,403













Cash Flow Statement (000's)












Net Income

51,724

3,795

14,559

26,967

6,403

Depreciation

14,340

0

2,351

8,582

3,407

Working Capital

0

(567)

(2,645)

(1,470)

3,160

Operating Cash Flow

66,064

3,227

14,265

34,079

12,970







Capital Costs






Capitalized Development

(13,740)

0

(6,870)

(5,972)

(899)

Mine Capital

(600)

0

(400)

(200)

0

Total Capital

(14,340)

0

(7,270)

(6,172)

(899)







Net Cash Flow

50,202

3,227

6,995

27,908

12,072

Cumulative Cash Flow


3,227

10,222

38,130

50,202

Project economics remain positive with a wide range of variations in operating costs, capital costs and gold prices.  The project also maintains a positive outlook with changes to both capital and operating cost as is demonstrated in the following table:


Variance

-40%

-20%

0%

20%

40%

Gold Price

NPV($M)

$7.1

$33.9

$60.7

$87.4

$114.2

PI

1.56

3.66

5.76

7.87

9.97








Oper.

Costs

NPV($M)

$84.9

$72.8

$60.7

$48.6

$36.5

PI

7.66

6.71

5.76

4.81

3.86








Capital Costs

NPV($M)

PI

$65.7

$63.2

$60.7

$58.1

$55.6

9.60

7.20

5.76

4.80

4.12

Notes:

1.

Profitability Index (PI) is the ratio of the present value of cash flows to investment.

2.

The internal rate of return is undefined when the cash flow is positive for all years of the project including the first year.

Recommendations for the Pinson underground are to expand the current underground contract mining program from 4 shifts per week to a full-scale production schedule, to continue mining mineral reserves accessed by the existing development and to resume development of the Pinson Spiral in Q1 2015. Underground drilling will be required to convert additional resources to reserves to extend mine life.

Mag Open Pit Project

Golder was commissioned to produce a Technical Report for the Mag Open Pit at a level sufficient to support an updated new Mineral Reserve estimate as part of a Preliminary Feasibility Study for the project. The Mag Open Pit resource is lower grade, disseminated, and near surface. It is suitable for exploitation by surface mining methods. This resource is spatially separated from the higher grade, more structural controlled resource at Pinson that has been defined for the underground project. The Mag Open Pit mineral resource as previously reported in the May 18, 2012 Technical Report, are shown in the following table. The grade of mineralization shown reflects total gold grade in ounces per ton (opt).

Mag Open Pit Mineral Resources

Open Pit Mineral Resource by Area, 0.010 opt Au Cutoff

Zone

Measured

Indicated

Measured + Indicated

Inferred

Tons

(1,000)

Gold

Grade

(opt)

Gold

Ounces (1,000)

Tons (1,000)

Gold

Grade

opt

Gold

Ounces

(1,000)

Tons

(1,000)

Gold

Grade

opt

Gold

Ounces

(1,000)

Tons

(1,000)

Gold

Grade

opt

Gold

Ounces

(1,000)

Mag Pit

20,631

0.034

711

2,704

0.074

201

23,335

0.039

912

533

0.038

20

South Zone

528

0.040

21

1,604

0.030

49

2,131

0.033

70

291

0.028

8

Summary

21,159

0.035

732

4,307

0.058

250

25,466

0.039

982

824

0.034

28

The life-of-mine reserves for the open pit are shown in the following table are based on a gold price of $1,250 per ounce for the open pit operations. Mine reserves are calculated at an internal cyanide soluable gold cutoff grade of 0.0064 opt at $1,250 per ounce. Cyanide soluble gold grade (AuCN), versus total gold grade, was utilized to drive the reserve estimate for the Mag Open Pit estimate due to the presence of refractory sulfide, non-heap leach recoverable gold mineralization in the resource.

Mag Open Pit Mineral Reserves

Reserve Summary at 0.0064 opt AuCN Cutoff (Imperial)

Zone

Proven

Probable

Proven + Probable

Ounces

Tons

(1,000)

Grade

(opt)

Ounces

Tons

(1,000)

Grade

opt

Ounces

Tons

(1,000)

Grade

opt

Mag Pit

Au

250,579

6,323

0.0396

72,065

837

0.0861

322,644

7,160

0.0451

Mag Pit

AuCN

140,554

6,323

0.0222

43,047

837

0.0514

183,600

7,160

0.0256

Note: Grade reported in both total gold grade (Au) & heap leach recoverable gold (AuCN)

The reserves are currently constrained based on the limits of private fee owned, non-public property that contain those portions of the Mag Pit mineralization zones within Sections 33 and 28 of the mine property. Substantial additional resource is located outside of these boundaries on publicly owned property. This additional resource should be studied in the future as a potential project expansion, but would require additional permitting to develop.

The mining method proposed for the Mag Pit consists of traditional drill and blast operations followed by loading rear-dump haul trucks for ore transport to the crushing plant and the waste rock storage facility. A fleet of 100-ton haul trucks and 16 cubic yard wheel loaders will be utilized. The mining fleet has been selected to match the mine plan target production rate of 1.5 million ore tons per year. The proposed mining schedule employs two ten-hour shifts per day, seven days per week. This study assumes that new mining equipment is purchased and self-mined by Atna employees.  

Metallurgical test work supports the processing of the Mag Pit ores by crushing, heap leaching, with metal recovery by carbon adsorption, desorption, and recovery by electrowinning. The development plan for the Mag pit envisions two-stage crushing, and recovery by heap leaching and gold recovery in an ADR plant.

The Mag open pit mine is projected to have a life of 6 years with a payback of 4.4 years at a gold price of $1,300 per oz. The project's expected cash-operating cost is estimated to be $627 per oz of gold. The cash flow assumes that all equipment, including mining equipment, is purchased outright versus being financed over time or purchased used, which is the more likely outcome for development. Contract mining was not reviewed as an option, but, due to the relatively short project life, would likely improve economic returns and reduce up-front capital cost. Additionally, run-of-mine leaching, the recovery method historically used at Pinson, may also be a viable option for reducing capital cost and increasing overall returns.

Economic analysis of the Mag Open Pit project, at a gold price of $1,300 per oz shows a pre-income tax Net Present Value @ 8% (NPV8) of $28.1 M after inclusion of the Nevada Net Proceeds tax using a 0.0064 opt cyanide soluble cutoff grade. This yields a rate of return of 19.5%. These results are estimated on a stand-alone basis with no operating synergies assumed from a potential combination of the underground mine at Pinson.

The capital and operating cost estimate for the Mag Open Pit Project have been developed assuming that it is developed and mined by Atna. Given the project's short mine life, the plan incurs minimal estimated sustaining capital. Estimated equipment salvage value (US$11.6M) is included in the yearly cash flow analysis shown below.

Summary of Open Pit Capital Cost Estimate (US$)

Item

Total

Open Pit Mine Capital (Initial and sustaining)

$25,657,274

Surface Facilities (Heap Leach Facility and Shop)

$9,788,000

Processing

$30,160,960

Misc: Bonding Cost

$1,273,000

Total

$66,879,234

Annual operating cash flows using a gold price of $1,300 per ounce are shown in the following table:

Mag Open Pit Estimated Yearly Production and Cash Flow Summary ($000s)


Year 1

Year 2

Year 3

Year 4

Year 5

Year 6

TOTAL

Production Statistics

Waste Tons Mined (000s tons)

11,965

8,528

7,561

1,355

558

96

30,064

Ore Tons Mined (000s tons)

391

1,547

1,474

1,540

1,531

678

7,160

Ore Tons Processed (000s tons)

380

1,521

1,510

1,521

1,521

707

7,160

Au Oz's Mined (Ounces)

5,519

39,198

27,314

41,166

46,412

23,991

183,601

Au Oz's Sold (Ounces)

4,195

31,115

30,166

37,842

45,153

35,130

183,601

Cumulative Oz's Sold (Ounces)

4,195

35,310

65,476

103,318

148,471

183,601

183,601

GROSS SALES REVENUE ($000) @ $1,300/oz

$5,453

$40,450

$39,216

$49,194

$58,699

$45,669

$238,681

Selling Costs @ $ 1.57/oz ($000)

$7

$49

$47

$59

$71

$55

$288

NET SALES REVENUE ($000)

$5,446

$40,401

$39,169

$49,135

$58,628

$45,614

$238,393

Cash Production Costs ($000)

Direct Operating Costs

$14,031

$22,675

$23,168

$16,881

$15,962

$8,031

$100,748

Mine Indirect Costs

$1,365

$1,362

$1,359

$1,224

$1,171

$1,164

$7,644

Royalties

$138

$848

$609

$1,312

$2,274

$1,403

$6,583

TOTAL CASH COSTS ($000)

$15,534

$24,885

$25,136

$19,416

$19,406

$10,598

$114,976

Cash Cost Per Au oz ($/oz)

$2,814

$635

$920

$472

$418

$442

$626

EBITDA ($000)

($10,087)

$15,515

$14,033

$29,719

$39,221

$35,016

$123,417

EBITDA Per Au Oz ($/oz)

($1,828)

$396

$514

$722

$845

$1,460

$672

Capital Expenditures ($000)

$66,521

$0

$0

($4,461)

($502)

($6,309)

$55,248

 Nevada Net Proceeds Taxes ($000)

$7

$439

$353

$1,173

$1,679

$1,441

$5,092

NET-PRE INCOME TAX CASH FLOW ($000)

($76,615)

$15,076

$13,680

$32,313

$38,045

$39,885

$63,078

Pre-Tax Cash Flow Cumulative ($000)

($76,615)

($61,538)

($47,859)

($14,852)

$23,193

$63,078

$63,078

Federal Income Tax

$0

$0

$0

($836)

($5,806)

($8,319)

($14,960)

NET AFTER TAX CASH FLOW ($000)

($76,615)

$15,076

$13,680

$32,171

$32,239

$31,566

$48,117









NPV PRE-TAX ($000) = $28,133 at 8% – IRR = 19.5%

NPV AFTER-TAX ($000) = $18,325 at 8% - IRR = 16%

Mag Open Pit Project Economic Summary

Gold Price $/oz

$1,300

Total Au Ozs

183,600

Pre-Tax NPV 8%

$28,133,0002

After-Tax NPV 8%

$18,325,000

Pre-Tax IRR

19.5%

Pre Tax Payback (yrs)

4.4

Cash Cost/Oz (operating)

$627

The following table shows the results of +10% changes in price, OPEX, and CAPEX assumptions. It is apparent that the NPV is more sensitive to sale price than capital or operating costs changes.

Open Pit Sensitivity Analysis for Price, OPEX, CAPEX ($000s)

%Change

Pre-Tax NPV

@ 5%

Pre-Tax NPV

@ 8%

Pre-Tax NPV

@ 10%

Price

-10%

20,726

11,551

6,327

0

39,252

28,133

21,768

+10%

57,926

44,854

37,343

Operating Cost

-10%

48,535

36,643

29,817

0

39,252

28,133

21,768

+10%

29,968

19,623

13,720

Capital Cost

-10%

44,710

33,533

27,124

0

39,252

28,133

21,768

+10%

33,794

22,733

16,413

There are approximately 183,600 ounces of recoverable gold in proven and probable reserves at a 0.0064 opt (AuCN) cutoff within that portion of the Mag Pit mineralization zone constrained by private lands controlled by Atna. Potential to develop additional mineralized resource exists. This development will require pit expansion beyond the limits of the private fee-owned lands onto federal lands managed by the United States Department of the Interior Bureau of Land Management and is not under consideration at this time. Additional study is recommended to evaluate the additional potential to develop these resources in conjunction with the recommended metallurgical testing discussed below.

Due to the short life of the project, the purchase of used mining equipment to reduce initial capital costs is a viable alternative and should be studied. Alternatively, the use of a contract miner may provide capital cost reduction, but with a likely increase in operating costs.

Additional stand-alone and stacked column leach testwork is recommended to further understand the impacts on gold recovery of varying cyanide soluable gold content and the degree of preg-robbing under leach conditions mimicking those anticipated for the industrial heap leach. Additional test regarding energy consumption used in crushing and run-of-mine size and recovery tests are recommended. Run-of-mine leaching was the past operating practice at Pinson: it may eliminate or reduce the need for crushing plant capital and should be studied.  

Submitting a Mine-Plan-of-Operations is the next step required to commence the permitting process. This study provides the basis for that next step.  

For additional information on Atna Resources and the Pinson mine, please visit our website at www.atna.com.

This press release contains certain "forward-looking statements," as defined in the United States Private Securities Litigation Reform Act of 1995, and within the meaning of Canadian securities legislation relating to potential optimization, increased productivity, cost reduction, economics, or resource or reserve expansion at the Pinson mine. Forward-looking statements are statements that are not historical fact. They are based on the beliefs, estimates and opinions of the Company's management on the date the statements are made and they involve a number of risks and uncertainties. Consequently, there can be no assurances that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update these forward-looking statements, if management's beliefs, estimates or opinions, or other factors, should change, unless required by law. Factors that could cause future results to differ materially from those anticipated in these forward-looking statements include: gold deposit modeling, future operating costs at the Pinson mine, the Company might encounter problems such as the significant depreciation of metals prices; accidents and other risks associated with mining, exploration and development operations; the risk that the Company will encounter unanticipated geological factors; the Company's need for and ability to obtain additional financing; the possibility that the Company may not be able to secure permitting and other governmental clearances necessary to carry out the Company's exploration and development programs; and the other risk factors discussed in greater detail in the Company's various filings on SEDAR (www.sedar.com) with Canadian securities regulators and its filings with the U.S. Securities and Exchange Commission, including the Company's 2013 Form 20-F dated March 14, 2014.

Cautionary Note to U.S. Investors --- The United States Securities and Exchange Commission permits U.S. mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. We use certain terms in this report, such as "measured," "indicated," "inferred," and "resources," that the SEC guidelines strictly prohibit U.S. registered companies from including in their filings with the SEC.

FOR FURTHER INFORMATION, CONTACT:

James Hesketh, President and CEO - (303) 278-8464
Valerie Kimball, Investor Relations - toll free (877) 692-8182
www.atna.com

SOURCE Atna Resources Ltd.


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Atna Resources Ltd.
Bergbau
-
-
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"