Orocobre Limited Construction Update on the Olaroz Lithium Project

22.09.2014  |  ABN Newswire
Perth, Australia (ABN Newswire) - Orocobre Ltd. (ASX:ORE) (TSE:ORL) ("Orocobre" or "the Company") is pleased to advise progress on the construction and commissioning at its flagship Olaroz Lithium Project. In terms of physical progress the construction program is now nearing completion with the commissioning of circuits occurring as they are released from construction. The project is expected to be completed on budget.


Construction Activities

Key construction activities in the lithium carbonate plant in recent times have been the mounting of carbon steel and stainless steel pipework, the installation of air compressors, tanks and air treatment, the assembly and installation of the Bepex micronizing equipment and fitment of heating ducts and air supply.

As previously advised in the Company's last construction update, the Company has been assisting some construction contractors with the procurement and importation of some materials. One of these materials has been PVDF* piping which was being sourced from Europe. Unfortunately, in spite of the Company's assistance, this piping arrived later than scheduled causing minor delay in the completion of the piping on a number of circuits and the hand-over from construction to commissioning. Consequently, the expected time for the lithium plant to be operational, including purification and micronizing circuits, has been delayed by approximately three weeks with the plant scheduled to be operational in the second week of November.

*Polyvinylidene Fluoride (PVDF) is a unique thermoplastic with properties which allow it to be used for very aggressive or highly specialised applications. Although expensive compared to other thermoplastics, PVDF offers an economically attractive alternative to many "exotic" materials in process lines where limited working life of other materials necessitates frequent replacement.


Commissioning and Production

Commissioning of the soda ash system, air compressors, industrial water supply and reverse osmosis plant, brine pumps to the carbonate plant, boilers and process tanks is in progress or has been completed.

The gas fired electricity generation plant commissioned in July continues to operate smoothly and provide all the power requirements. The liming plant, which is used to treat brine to remove magnesium, is operating in automatic mode at a rate of 230l/s compared to a design rate of 200l/s and is expected to reach a rate of 250 l/s over coming weeks. Pond filling from the bore field is operating at 200l/s compared to a design rate of 180l/s and is expected to peak at more than 230l/s with the commissioning in October of a final bore.

The Company continues to follow the community and shared value policy to successfully work with suppliers and the employment bureau to focus on the hiring of local people from the communities of Olaroz, Huancar, Puesto Sey, Pastos Chicos, Catua, Susques, Jama, El Toro, Coranzulí, San Juan and Abrapampa. The project implementation is through EPCM (Engineering, Procurement and Construction Management) with a high proportion of local involvement through construction and supply contracts and local employment. The community and shared value policy continues to be a key success factor, training local people under the supervision of high quality experienced professionals.

The Olaroz lithium project is being developed by Orocobre (66.5%) with partners Toyota Tsusho Corporation ("TTC") (25%) and the Jujuy Province mining and energy company, JEMSE (8.5%) with a construction budget of US$229m including contingency.

To view photographs, please visit:
http://media.abnnewswire.net/media/en/docs/ASX-ORE-818944.pdf


About Orocobre Limited:

Orocobre Ltd. is listed on the Australian Securities Exchange and Toronto Stock Exchange (ASX:ORE) (TSE:ORL), and is building a substantial Argentinian-based industrial minerals company through the construction and operation of its portfolio of lithium, potash and boron projects and facilities in the Puna region of northern Argentina. The Company is building in partnership with Toyota Tsusho Corporation the first large-scale, "greenfield" brine based lithium project in 20 years at its flagship Salar de Olaroz resource, with projected production of 17,500 tonnes per annum of low-cost battery grade lithium carbonate scheduled to commence at the end of Q2, 2014. The Company also wholly-owns Borax Argentina, an important regional borate producer. Orocobre is included in the S&P/ASX 300 Index and was named 2012 Mining Company of the Year by Argentine mining magazine Panorama Minero and the Fundacion para el Desarrollo de la Mineria Argentina ("Fundamin" or Foundation for Development of Argentina Mining).



Contact:

Orocobre Ltd.
David Hall, Business Development Manager
T: +61 7 3871 3985
M: +61 407 845 052
E: dhall@orocobre.com

James Calaway, Chairman
M: +1 (713) 818 1457
E: jcalaway@orocobre.com
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Allkem Ltd.
Bergbau
-
-
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"