Diamond Drilling Results from the La Cobota Copper Project, Mexico

11.02.2016  |  Marketwired

TORONTO, ONTARIO--(Marketwired - Feb. 10, 2016) -

NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES

Era Resources Inc. ("Era" or the "Company") (TSX:ERX) is pleased to announce the results of the recent initial diamond drilling program at the La Cobota Project ("La Cobota" or the "Project") located in Sonora, Mexico.

The Project comprises three contiguous mining concessions that together encompass approximately 1,800 hectares. The concessions are situated in the mining-friendly jurisdiction of Sonora State, Mexico, and are located on privately held land approximately 80 kilometres east-southeast of the town of Sonoyta and 10 kilometres south of the US border (Figure 1). The project area is easily accessible via existing roads and unsealed ranch tracks. Era is party to an option agreement for the mining concessions and has undertaken the drilling as part of a systematic exploration program to assess the prospectivity of the mining concessions.

During the period from mid-December 2015 to mid-January 2016, Era completed eight diamond drill holes totaling 955.60 metres at La Cobota (Table 1 and Figure 2). All drill holes were HQ size (63.5 milimetres diameter) and core recovery was excellent. The drill program was designed to test the continuity and grade of an outcropping mineralized structure that was the focus of historical underground mining operations. Assay results from the drilling (Table 2) confirm the presence of high grade copper-silver mineralization and suggest that the mineralization occurs within a north-east plunging shoot.

Mineralization at La Cobota is hosted within a complex iron-oxide vein system that transects an equigranular to porphyritic quartz monzonite intrusion. The principal vein (Vein #1, Figure 2) targeted by drilling is heavily oxidized and composed of massive to semi-massive magnetite and hematite. Copper mineralization principally occurs as fine-grained chalcocite, with some native copper and other copper oxides. Minor remnant chalcopyrite and pyrite is also observed. The vein is faulted and brecciated to a variable degree; and is locally intruded by mafic dykes that appear to stope-out the mineralization. Drilling intersected a major fault beneath the historical mine workings that juxtaposes the quartz monzonite against a polymictic meta-conglomerate unit. This fault is interpreted to be a thrust structure that may truncate the mineralized vein at depth.

Under the terms of the option agreement for the La Cobota mining concessions, Era has an exclusive right to conduct exploration and is responsible for all land taxes and annual concession or permit fees during the option period, which ends on July 1, 2016. The Company has the right to acquire 100% of the concessions for a fixed amount of US$275,000, subject to a 2.5% Net Smelter Return royalty interest granted to the vendor of the mineral concessions, once it elects to proceed with the acquisition.

"The assay results from the diamond drilling at La Cobota suggest that the mineralized iron oxide vein has significantly more structural complexity and grade variability than was originally anticipated from surface mapping and the available historical mining records. Work is continuing to assess the viability of the mineralized structure to host a resource and the Company will make a decision on the La Cobota option in due course," said Chief Executive Officer Pieter Britz.

The scientific and technical information in this press release was authorized by Mr. Lachlan Reynolds, BSc, MAusIMM, MAIG. Mr. Reynolds is the Vice President, Business Development of Era Resources Inc. and is a Qualified Person for the purposes of NI 43-101.

To view Figure 1: Location of the La Cobota Project, Sonora, Mexico, please visit the following link: http://media3.marketwire.com/docs/1042609Figure1.pdf

Diamond Drilling Program

A total of eight diamond drill holes were completed at the Project (Figure 2), for a total of 955.60 metres of drilling (Table 1). Seven of these holes (15LC001-006 and 16LC007) were targeted at the main mineralized structure (Vein #1), which was the principal site of historical mining operations. An eighth and final hole was subsequently completed to test a number of mapped veins in the hanging wall to the northwest of Vein #1.

Table 1: Summary of diamond drilling completed at the La Cobota Project
Hole ID   Coordinates*   Azimuth
(°)
  Inclination
(°)
  Depth
(m)
  Date
Completed
  East (m)   North (m)  
15LC001   396,228   3,490,725   164   -75   203.55   09/12/2015
15LC002   396,231   3,490,727   164   -50   110.75   11/12/2015
15LC003   396,307   3,490,728   191   -70   90.70   13/12/2015
15LC004   396,307   3,490,728   191   -85   91.10   15/12/2015
15LC005   396,308   3,490,729   140   -70   94.80   17/12/2015
15LC006   396,308   3,490,729   140   -85   95.65   19/12/2015
16LC007   396,351   3,490,744   140   -70   106.35   09/01/2015
16LC008   396,140   3,490,783   180   -60   162.70   13/01/2016
Total:                   955.60    
*Coordinate datum NAD84, UTM Zone 12N

To view Figure 2: La Cobota Project drill status plan, please visit the following link: http://media3.marketwire.com/docs/1042609Figure2.pdf

Assay Results

A total of 264 half-core samples were collected from the drill core using a diamond blade saw. Samples were transported to the Bureau Veritas ("BV") sample preparation laboratory in Caborca, Mexico. Gold fire assays were subsequently completed at the BV analytical laboratory in Hermosillo, Mexico. A multi-element assay suite was analyzed at the BV analytical laboratory in Vancouver, Canada.

A quality assurance/quality control ("QA/QC") procedure adopted by the Company confirms that assay results are reliable. This procedure included routine analysis of blank samples and certified standard reference materials. In addition, BV implemented an internal QA/QC procedure consisting of blanks, duplicates, repeats and standard reference materials.

Significant mineralized intersections from the diamond drilling are shown in Table 2. Intersections have been calculated using a 0.1% Cu cut-off, including a maximum of 1 metre of internal dilution. Higher grade zones have been calculated using a 0.5% Cu cut-off, including a maximum of 1 metre of internal dilution.

Full drill results will be available on the Company's website.

Table 2: Mineralized intersections from La Cobota diamond drilling program
Hole ID   From
(m)
  To
(m)
  Length*
(m)
  Cu
(%)
  Ag
(ppm)
  Comment
15LC001   7.6   10.6   3.0   0.18   0.63   No significant intersections
    64   67   3.0   0.19   1.00    
15LC002   59.2   60.2   1.0   0.10   2.50   No significant intersections
15LC003   18.35   19   0.65   0.65   3.00    
    23   28.15   5.15   0.59   1.59   Vein #2
including   24.5   27.45   2.95   0.92   2.12    
    55.8   63.4   7.6   0.65   2.99   Vein #1
including   60.4   63.4   3.0   1.25   5.67    
15LC004   19.9   25   5.1   0.30   1.17   Vein #2
including   20.95   21.95   1.0   0.97   2.10    
    68.2   74.95   6.75   0.21   0.91   Vein #1
15LC005   18.2   19.75   1.55   1.42   3.57   Vein #2
including   18.95   19.75   0.8   2.49   5.70    
    66.65   75.82   9.17   1.27   20.45   Vein #1
including   68.8   75.82   7.02   1.60   26.38    
including   68.8   71.4   2.6   2.76   53.75    
15LC006   18.3   19.85   1.55   1.25   3.37   Vein #2
including   19.3   19.85   0.55   3.30   8.60    
    24.75   27   2.25   0.60   0.73    
including   24.75   25.75   1.0   0.84   0.70    
    74.2   81.6   7.4   0.15   0.46   Vein #1
16LC007   4.4   6.75   2.35   0.44   4.53    
    12   19   7.0   0.38   2.18    
including   17.7   18.4   0.7   1.50   4.80    
    20.75   24.25   3.5   1.62   3.52   Vein #2
including   21.6   23.35   1.75   3.06   4.75    
16LC008   32.75   43.3   10.55   0.19   0.95   Vein #4
* Downhole length, close to true width due to the angle of drilling intersections with vein structures

This news release does not constitute an offer to sell or the solicitation of an offer to buy any ordinary shares within the United States. The ordinary shares have not been offered and will not be registered under the United States Securities Act of 1933, as amended (the "1933 Act"), or any state securities laws. Accordingly, the ordinary shares may not be offered or sold in the United States or to U.S. persons (as such terms are defined in Regulation S under the 1933 Act) unless registered under the 1933 Act and applicable state securities laws or an exemption from such registration are granted.

Cautionary Statement Regarding Forward-Looking Information

This news release contains forward looking information. Such forward-looking information is often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect" and "intend" and statements that an event or result "may", "will", "should", "could", or "might" occur or to be achieved and any other similar expressions.

In providing the forward-looking information in this news release, the Company has made assumptions regarding the accuracy of exploration results received to date. Although management believes that the assumptions made and the expectations represented by such information are reasonable, there can be no assurance that the forward-looking information will prove to be accurate. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that could cause actual results to differ materially from those contained in the forward-looking information. Some of these risks, uncertainties and other factors are described under the heading "Risks Factors" in the Company's annual information form available on the Company's profile on SEDAR at www.sedar.com. Forward-looking information is based on estimates and opinions of management at the date the statements are made. Except as required by law, Era does not undertake any obligation to update forward-looking information even if circumstances or management's estimates or opinions should change. Readers should not place undue reliance on forward-looking information.

Factors that could cause actual results to vary materially from results anticipated by such forward-looking statements include the actual results of exploration activities, changes in market conditions, risks relating to international operations, fluctuating metal prices and currency exchange rates, and other risks of the mining industry. Although Era has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Era undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change except as required by applicable securities laws. The reader is cautioned not to place undue reliance on forward-looking statements. Statements concerning mineral reserve and resource estimates may also be deemed to constitute forward-looking statements to the extent they involve estimates of the mineralization that will be encountered if the property is developed. Reference is made to the most recent annual information form of Era available on the Company's profile on SEDAR at www.sedar.com which includes further discussion of the risk factors which may impact the business and operations of Era.



Contact

Era Resources Inc.
Pieter Britz
President & Chief Executive Officer
+61 400 666980
pb@eraresources.com

Era Resources Inc.
Alex Dann
Chief Financial Officer & Corp. Secretary
+1 416 464 4067
ad@eraresources.com
www.eraresources.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Era Resources Inc.
Bergbau
-
-
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"