Suche
 
Folgen Sie uns auf:

Gratomic Inc Provides Update on Construction of Commercial Scale Graphite Processing Plant and Exploration Activities at Aukam Mine, Namibia

03.05.2019  |  PR Newswire

TSX-V: GRAT

TORONTO, May 3, 2019 - Gratomic Inc. ("Gratomic" or the "Company") (TSX-V: GRAT) (CB81–FRANKFURT) a vertically integrated graphite to graphene, advanced materials development company is pleased to provide an update from its Aukam Graphite Mine in Namibia. The Company has been advancing the Graphite Project on three fronts focusing on exploration and diamond drilling, construction of on-site offices, laboratory, and living quarters, and the construction of a commercial scale graphite processing plant. The commercial scale graphite plant, capable of producing in excess of 20,000 tonnes of graphite concentrate per year, will replace the existing pilot plant commissioned in 2018 which successfully produced 5.5 tonnes of graphite concentrate grading between 88%-96% Carbon as Graphite ("Cg").

The Aukam Graphite Project is located in southern Namibia close to the port city of Luderitz. The property hosts five underground adits which were mined periodically between 1940 and 1974.  Graphite mineralization at Aukam is of the vein or lump type and occurs as massive lenses and veins. Graphite has also been observed as minor disseminated patches hosted in variably altered granite.

2018 Exploration

During 2018, Gratomic contracted Gregory Symons Geophysics (GSG) to perform Horizontal Loop Electromagnetics (HLEM) and magnetic surveys in continuation of previous geophysical surveys undertaken in 2016/2017.  The original survey was performed in the vicinity of the Aukam Mine marked by the black polygon in Figure1 below.  During the 2018 geophysical survey, ground electromagnetic and magnetic surveys were completed in two areas identified as Grid 1, which lies East of the Aukam Mine, and a portion Grid 2 as indicated in purple, known as Snyman Graphite Occurrence (see Figure 1).

Grid 1 adjoins the previous survey over the mine area at Aukam and extends the strike length covered to 1.6 kilometres to the East. Significant interpretations pertaining to Grid 1 include:

  • Graphite identified at surface occurs both as massive graphite veins and widespread disseminated graphite over an area of 550 metres east-west by 190 metres north- south,
  • Surface graphite showings are located sub-parallel to known electromagnetic anomalies,
  • Electromagnetic anomalies extend those depicted by the original survey by approximately 550 metres,
  • Current strike length of anomaly now stands at 1.3 kilometres,
  • Distinct drill targets have been identified along the trend (see Figure 2),
  • Surveyed area appears to be under rather shallow sand cover,
  • Prospective areas identified are conducive to surface trenching.

Grid 2 of the completed geophysical survey covers the Snyman graphite occurrence in the northeastern portion of EPL3895. The Snyman graphite occurrence covers an area of 7.5 ha and lies approximately 6.5 kilometres east of the Aukam mine.

Significant interpretations pertaining to Grid 2 include:

  • Graphitic interpreted mineralization is depicted by a predominant EM anomaly in the northwest part of the grid extending over 150 metres,
  • A second weaker EM further to the east extends over 600 metres is thought to be associated with graphite mineralization in the area
  • The grid area appears to be covered with thin overburden,
  • Areas have been identified as prospective areas conducive to surface trenching (see Figure 3)

During 2018 Gratomic was granted additional Exclusive Prospecting License, Number 6710 (EPL 6710) by the Namibian Ministry of Mines and Energy, with an initial exclusivity of three years.  The license area is contiguous with EPL 3895, which covers the Aukam graphite deposit and the Snyman graphite occurrence (see Figure 4). The application for EPL 6710 was submitted in order to cover the potential strike extension of the Snyman graphite occurrence to the east. In addition, EPL 6710 covers an additional area considered prospective for graphite within the "Aukam window" where rocks hosting the Aukam and Snyman graphite are exposed beneath the regional unconformity at the base of the Nama Group sedimentary rocks. The addition of the new EPL increases the area of prospective geology covered to 63,072 hectares (630 square kilometres). 

Regional exploration in 2018 included mapping and sampling of graphite occurrences throughout the Company's license areas with emphasis on the 400 hectares encompassing both the Snyman graphite occurrence and the area east of the Aukam Mine. Compilation, interpretation and presentation of all available geologic data allowed for subsequent diamond drill targeting with initial drilling planned for the area immediately east of the existing underground workings of the Aukam Mine. 

Two company drills were deployed to Aukam in March 2019 with diamond drilling commencing in April.  The company is currently operating a Longyear 38 with a 2-cylinder XY-1 drill for a backup.  Initial targets being drilled are proximal to the Aukam Mine and are spaced at 25 metres with infill drill planned to follow based on results. Five holes have been completed at the time of this release.

Processing Plant

During 2018 Gratomic completed the construction and start-up of its' prototype processing plant to test and refine the processes that will be used for commercial production. The Aukam processing plant uses a simple crushing, grinding and flotation system. Graphite feed for the prototype plant was obtained from screening and sorting of existing stockpiles from historical mining. The processing plant operated for 26 days during April and for all 31 days in May of 2018. While operational, data was collected at each phase of the process and test results from samples were sent to Gecko labs with the subsequent results used to optimize plant processes. The following tests and optimization were conducted:

  • Liberation analysis
  • Flake size distribution analysis
  • Mixing velocity optimization
  • Screen size analysis and optimization
  • Air flow analysis in columns and optimization
  • Drying analysis and optimization
  • Silica dispersant ratio optimization
  • Reagent optimization
  • Product flow rate optimization
  • Grade optimization
  • Staff recruitment, training, and man-hour analysis
  • Economic sensitivity analysis on pilot processing facility
  • Feed stock optimization and process

The Company continued to optimize the pilot plant processing stockpiled graphite mineralization throughout 2018. To date, the plant has processed 9 tonnes of the graphite mineralization with 5.5 tonnes of graphite concentrate grading between 88% and 96% Cg shipped to Perpetuus Carbon Technologies ("Perpetuus") for the manufacture of graphene to be used in the automobile and bicycle tire industry. Graphene made from Aukam graphite continues to be tested in Europe and Asia with good results.

Gratomic and Perpetuus are currently in collaboration to build on Perpetuus' capability to produce high quality surface modified graphene in support of the anticipated volumes required by the tire manufacturing industry. Additional applications that have now been generated in a preproduction format include radiant heating membranes and super hydrophobic coatings with an addressable market that include; graphene inks, marine, oil & gas, power generation, industrial (repair & maintenance), infrastructure (new build) and automotive & transportation among others.

Plant Expansion

Plant expansion to increase capacity to 20,000 tonne per annum began in 2018. Initial activities included construction of a platform for drying graphite product and of a washing bay for equipment, complete with a containment system to collect impacted water. Steel drying pans, an oven, and two screens were also assembled and successfully tested. Continued upgrades involved the extension of the working area on the pilot plant by another 35 metres to the north-west to accommodate new crushing equipment and conveyor belts.  Analysis of all plant processes continues to optimize efficiencies of each process such as rod mills, flotation columns, and reagent introduction. Four different tests were run with the first test being used as a base line.  Samples were taken from the rod mill feed, mill discharge, and screen under-and-over size.  Calculations were made to determine the amount of chemicals needed to be introduced into the mixers according to the density and volume of the mixer feed.

Recent upgrades to the processing plant continue with the arrival of additional commercial scale equipment including; industrial sized generator, screw conveyors, shaker screens, rod mill, conveyors, and boom truck.

Gratomic is continuing with its systematic assembly of the commercial scale graphite processing plant.  Next steps will include:

  • Completion of the pilot acid wash. This circuit will be used to collect engineering data to design the commercial scale plant. This is an addition to the plant that will allow the company to produce upwards of 98.5% graphite based on its latest pilot testing results in the lab.
  • Modifications are currently being made to the jaw crusher to allow it to more effectively crush graphite,
  • Rod mill support systems such as maintenance cradles and cranes, rod loading equipment and control systems are currently being engineered,
  • Flotation circuit mass balances are being explored using pilot plant data in order to size the pumps and flow lines of the flotation system,
  • Dewatering circuit equipment are currently being specified,
  • Water conditioning systems are currently being designed to allow close to 100% recycle of water. This includes pH control, removal of fine suspended solids and removal of dissolved iron,
  • Control systems are being designed for each sub-circuit of the commercial scale plant.

Camp Construction

Construction of the onsite Management Camp consisting of offices, laboratory, kitchen, and living quarters, is ongoing.  Work began with two of the larger structures during Q4/2018.

Qualified Persons

Steve Gray, P.Geo. has reviewed, prepared and approved the scientific and technical information in this press release and is Gratomic Inc.'s "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

About Gratomic Inc.

Gratomic is an advanced materials company focused on mine to market commercialization of graphite products most notably high value graphene-based components for a range of mass market products. We are collaborating with a leading European manufacturer of graphene to use Aukam graphite to manufacture graphene products for commercialization on an industrial scale. The company is listed on the TSX Venture Exchange under the symbol GRAT. 

"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."

FORWARD LOOKING STATEMENTS: This news release contains forward-looking statements, which relate to future events or future performance and reflect management's current expectations and assumptions.  Such forward-looking statements reflect management's current beliefs and are based on assumptions made by and information currently available to the Company. Investors are cautioned that these forward-looking statements are neither promises nor guarantees and are subject to risks and uncertainties that may cause future results to differ materially from those expected. These forward-looking statements are made as of the date hereof and, except as required under applicable securities legislation, the Company does not assume any obligation to update or revise them to reflect new events or circumstances. All of the forward-looking statements made in this press release are qualified by these cautionary statements and by those made in our filings with SEDAR in Canada (available at www.sedar.com).

For further information visit the website at www.gratomic.ca or contact: Arno Brand, Co-CEO, +1 416-561-4095, E-mail inquiries: abrand@gratomic.ca 


View original content:http://www.prnewswire.com/news-releases/gratomic-inc-provides-update-on-construction-of-commercial-scale-graphite-processing-plant-and-exploration-activities-at-aukam-mine-namibia-300843583.html

SOURCE Gratomic


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Gratomic Inc.
Bergbau
A2PWQP
CA38900X2077
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"