South Star Mining Announces Positive Pre-Feasibility Study Results and Maiden Reserve Estimate for Santa Cruz Graphite Project
Phase 1 consists of a pilot plant with the capacity to produce 5,000t of concentrate per year, and the simple layout includes a small open-pit processing plant with filtered tails technology, waste storage facility for co-disposal of wasterock and filtered tails and civil infrastructure. The goal of the Phase 1 operations is to test and optimize the flowsheet, develop the key commercial relationships and optimize the production of products demanded in the marketplace, given the inherent, high-quality nature of the concentrates produced to date. Detailed engineering of the pilot plant was completed as part of the PFS.
Phase 2 is a larger plant with similar layout and technology, but with a capacity of 25,000t of concentrate per year. It's important to highlight that both Phases include the use of filtered tails technology and co-disposal of tailings with wasterock to avoid the requirement of a Tailings Storage Facility. This is essential in facilitating the permitting process and decreasing the environmental footprint of the facility.
PFS Highlights
-
- Combined Maiden Proven & Probable (P+P) Reserve Estimate of 12.3M tonnes with strong conversion of resource to reserves.
- The Mineral Reserve Estimate is listed below:
Mineral Reserve Estimate | Tonnage | Cg | In-situ Graphite |
(t) | (%) | (t) | |
Proven | 3,989,635 | 2.49 | 99,340 |
Probable | 8,318,795 | 2.35 | 195,490 |
Total P &P | 12,308,500 | 2.40 | 295,400 |
Notes:
-
1)Mineral Reserves are as defined by the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves.
-
2)Mineral Reserves are based on Mineral Resources (Published on July 8th, 2019) estimated using ordinary kriging method and a three-dimensional block model using a cut-off grade of 0.75% and 1% Cg, depending on the modeled zones.
-
3)Numbers have been rounded.
-
4)Mineral Reserves have incorporated cut-off, pricing, costs, recovery & FX.
-
- Phase 1 Average Production of 5,000 tpy of 95% Cg Concentrate in Years 1 & 2
- Phase 2 Ramping up from 13,500 tpy of 95% Cg Concentrate in Year 3 to an average production of 25,000 tpy in years 4-11
- Average Basket Price of Products of US$1,287/t
- Open-pit mining with strip ratio of 1.6 Life of Mine (LOM)
- 12-Year LOM
- Exchange Rate of R$3.95 to US$1.00
- Post-Tax NPV5% of US$81.2M and internal rate of return of 35%
- US$129M Post-tax Cash Flow LOM
- Payback Period of 4 years
- CAPEX & OPEX Parameters for Each Phase are listed below:
Parameter | Phase 1 (US$) | Phase 2 (US$) | Phase 1 & 2 (US$) |
CAPEX | 7.3M | 27.2M | 34.5 |
OPEX ($/t Concentrate) | 604 | 386 | 396 |
-
- Sensitivity Analysis for NPV using CAPEX, OPEX, Sales Price and FX as follows:
Click Image To View Full Size
Richard Pearce, President and CEO of South Star, commented: "We have now submitted all the required permitting and licensing documents for the Phase 1 production facilities. We have a PFS highlighting a project with robust economics, low capital intensity, and low OPEX designed around a simple, proven flowsheet in one of the most prolific, high-quality graphite producing regions in the world. The detailed design of the Phase 1 facility is complete.
This is another important step on our path to production. Pilot plant operations with a very modest CAPEX are expected to provide short-term cash flow from operations and allow us to qualify bulk samples in the marketplace and establish future, firm offtake agreements. We have been working diligently to develop commercial relationships with key players, both in Brazil and internationally, and have received excellent feedback on our sample materials shipped to date. We will monitor closely the permitting and licensing process and will be using the first half of 2020 to get the financing in place to construct and commission the pilot plant facilities. Phase 1 construction is expected to take approximately 8-10 months. We are excited to be moving past project development and focusing all our efforts and attention on near-term construction, commissioning and production."
The technical information contained in this news release pertaining to the Santa Cruz Graphite Project has been prepared, reviewed and approved by Luiz Eduardo Pignatari, an independent qualified person under National Instrument 43-101-Standards of Disclosure for Mineral Projects ("NI43-101"). The qualified person has verified the information disclosed herein, including the sampling, preparation, security and analytical procedures underlying such information, and is not aware of any significant risks and uncertainties that could be expected to affect the reliability or confidence in the information discussed herein.
About South Star Mining Corp.
South Star Mining Corp. is focused on the selective acquisition and development of near-term mine production projects in Brazil to maximize shareholder value. STS has an experienced executive team with a strong history of discovering, developing, building and operating profitable mines in Brazil.
The Santa Cruz Graphite Project is located in Southern Bahia in the third largest graphite producing region in the world with over 70 years of continuous mining. The Project has at surface mineralization in friable materials, and successful large-scale pilot plant testing (>30t) has been completed. The results of the testing show approximately 65% of Cg concentrate is +80 mesh with good recoveries and 95-99% Cg. With excellent infrastructure and logistics, South Star is carrying its development plan towards production projected at the end of 2020.
To learn more, please visit the Company website at http://www.southstarmining.ca.
On behalf of the Board,
Mr. Richard Pearce
Chief Executive Officer
Ph: +1 (314)266-0793 (US)
Ph: +55 (11) 2308-6839 (Brazil)
Email: richard@southstarmining.ca
For additional information, please contact:
Mr. Dave McMillan
Chairman
Ph: +1 778-773-4560
Email: davemc@telus.net
Mr. Eric Allison
Director
Ph: +1 203 918-3098
Email: eric@southstarmining.ca
CHF Capital Markets
Cathy Hume, CEO
Phone: 416-868-1079 x231
Email: cathy@chfir.com
CAUTIONARY STATEMENT
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.
Forward-Looking Information
The information contained herein contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements."
Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to gold price and other commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.
Copyright (c) 2020 TheNewswire - All rights reserved.