Atacama Copper Provides Trenching Program Update at the El Cofre Copper-Gold Project

24.05.2022  |  Newsfile

Vancouver, May 24, 2022 - Atacama Copper Corp. (TSXV: ACOP) ("Atacama Copper" or the "Company") provides an update on its trenching program at its 100% owned El Cofre Copper-Gold Project.

Highlights:

  • 40% of 3,000m trenching program completed
  • Multiple zones of copper oxide mineralization identified
  • Over 156 samples collected and analyzed by XRF to date
  • Copper-gold mineralization identified across 1 to 5 meter wide mineralized veins over a strike length of 600m, with 800m remaining to be tested
  • Laboratory results expected in early June 2022

Gino Zandonai, CEO of Atacama Copper, said, "We are pleased to announce we are progressing on schedule with the trenching program on the El Cofre copper project, and we have confirmed the presence of copper mineralization along 600 meters strike into a 1.4km length of copper oxides occurrences corridor. This program is the first phase of a more extensive work program on the project. It is designed to gather additional targeting information and increase the knowledge of the type and geometry of the mineralization, which allows for identifying a number of high-priority target zones across the property."

Trenching program is currently 40% completed, including trenching, sampling, and mapping focused on the Viñita area. The overall trenching program is planned to excavate around 3,000 meters over 18 designed trenches and channel sampling lines focused on the northern section of the project area, the Viñita and Gloria areas. The program is targeting existing mapped mineralized structures and geochemical/geophysical anomalies. The completion of 18 trenches is subject to environmental evaluation and clearance, of which 70% of the planned trenches have already been approved for excavation.

The trench program to date has identified a fault-vein mineralized structure at Viñita, dipping 70° to the west and shows pockets of high-grade mineralization. In the Viñita South area the mineralised structure has been mapped along a strike length of at least 600 m in length. This sequence is part of a longer 1.4km long structural corridor of discontinuous mineralisation. The mapped mineralized fault-vein's vary between 1 to 5 meters in width with local combined structures up to 15 meters in width. The mapped veins are observed between 365 and 212 meters of elevation, which infers at least 150 meters of vertical continuity to the mineralization.

The geological mapping has been supported by XRF measurement. Channel and rock chip sampling are taken at one-meter intervals along the open trench. To date, referential XRF measurement (Olympus Delta) has been taken systematically over 156 samples in the company warehouse and by a certified operator to confirm and support the mineralization mapping of black oxides, copper-rich limonite, and copper oxides in general. The results from certified laboratory analysis of the samples are expected in early June 2022.

Geological map of El Cofre and location of completed trenches and channel sampling survey
(grades based on historical geochemistry results from previous operator)

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/7505/124778_0368410e34f32955_001full.jpg

Example of systematic sampling and outcropping mineralized vein in a trench

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/7505/124778_0368410e34f32955_002full.jpg

About Atacama Copper Corporation

Atacama Copper Corp. is a resource company focusing on acquiring, exploring, and developing copper properties in Chile. It is committed to advancing the exploration and development of the Placeton and El Cofre projects while looking to increase its asset portfolio through the acquisition and development of other high-value copper exploration, development, and production opportunities in Chile. Atacama Copper is currently focusing on exploring its Placeton project, an area located between the Relincho copper and El Morro Copper-gold projects of the Nueva Union project owned jointly by Teck and Newmont Mining.

Additional Information - Please Contact

For further information, please contact:

Atacama Copper Corp.
Gino Zandonai
Chief Executive Officer and Director
Email: info@atacamacopper.ca
Phone: +56 997 915 596

Qualified Person

The technical information contained in this news release has been reviewed and approved by Gino Zandonai of Atacama Copper Corp., a "Qualified Person" within the meaning of National Instrument 43-101.

Cautionary Statements

This news release contains "forward-looking information" and "forward-looking statements" (collectively, "forward-looking statements") within the meaning of the applicable Canadian securities legislation. All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that involves discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements.

In this news release, forward-looking statements relate to, among other things, statements relating to expectations regarding the exploration and development of the El Cofre and Placeton projects, including planned exploration and drilling activities, and other statements that are not historical facts. By their nature, forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or other future events, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Such factors and risks include, among others: the Company may require additional financing from time to time in order to continue its operations which may not be available when needed or on acceptable terms and conditions acceptable; compliance with extensive government regulation; domestic and foreign laws and regulations could adversely affect the Company's business and results of operations; the stock markets have experienced volatility that often has been unrelated to the performance of companies and these fluctuations may adversely affect the price of the Company's securities, regardless of its operating performance; and the impact of COVID-19.

The forward-looking information contained in this news release represents the expectations of the Company as of the date of this news release and, accordingly, is subject to change after such date. Readers should not place undue importance on forward-looking information and should not rely upon this information as of any other date. The Company undertakes no obligation to update these forward-looking statements in the event that management's beliefs, estimates or opinions, or other factors, should change.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking statements. Such factors include but are not limited to: the timing for receipt of final Exchange approval may not be received on the timelines expected or at all; general business, economic, competitive, political, and social uncertainties. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on the forward-looking statements and information contained in this news release. Except as required by law, the Resulting Issuer assumes no obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change, except as required by law.

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the TSXV) accepts responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/124778


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Fuerte Metals Corp.
Bergbau
CA35958L1013
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"