Suche
 
Folgen Sie uns auf:

Magnis Energy Technologies Limited: New York Lithium-ion Battery Plant Update

26.05.2022  |  ABN Newswire
Sydney, Australia - Magnis Energy Technologies Ltd. (ASX:MNS) (FRA:U1P) (OTCMKTS:MNSEF) is very pleased to provide an update on activities from Imperium3 New York ("iM3NY") which operates a Gigawatt scale Lithium-ion battery manufacturing plant in Endicott, New York. Magnis along with its joint venture and technology partner Charge CCCV LLC ("C4V") are the major shareholders in iM3NY.

Project Status and Recent Milestones

Overall project completion rate is at 72% at the end of April and on schedule to begin production late next month.

The completion rate is expected to be in the vicinity of 80% when fully automated production begins. The remaining 20% includes some cosmetic changes to the factory, minor works to an internal office area and the ramp up of production.

As the majority of advanced cell manufacturing equipment for high-volume production is installed, the iM3NY Lithium-ion Battery Plant produced hundreds of cells during April.

These cells will continue to undergo quality, reproducibility and performance checks to ensure smoother and efficient operation of high-volume production. Furthermore, some these cells are being used for qualification and certification purposes.

During April there was the commissioning of both mechanical and electrical facility utilities.

Commissioning is an important process in the manufacturing sector to ensure that all the incorporated and associated components (mechanical, electrical, process etc.), equipment and systems are installed, tested, operated and verified.

Safety - There were zero incidents in April.

New hires:

- 4 Operators
- 2 members in purchasing department
- 3 members in quality control department

Completed items during April 2022

- Installed utility piping within dry room spaces for process equipment

- Completed duct work installations in mixing rooms

- Utility fit up for Meier Drying Oven is completed

- Pressure testing of compressed air piping is completed

- NMP Solvent Condenser: Fabricated and installed

- Completed installation/Reassembly of Cathode Condenser

- Installed Anode and Cathode mixing room sprinkler system

- Continued installation of power distribution panels in high and low bay

- Continued commissioning of substations and power distribution panels

- Preparations for commissioning of space

- Completed installation of office space joists and metal deck

Items progressed during April 2022

- Continued installation of process gas piping on high bay utility rack

- Began installation of steam PRV stations at Munter's units.

- Continued installation of filling dry room systems

- Began installation of office space sprinkler system

- Continued installation of cell assembly plenum components

- Commissioning of filling and cell assembly dry rooms

iM3NY CEO Chaitanya Sharma commented: "After years of planning we are entering an exciting phase with fully automated production only weeks away. We look forward to keeping all stakeholders updated with all developments."

*To view photographs, please visit:
https://abnnewswire.net/lnk/2GW264P1



About Magnis Energy Technologies Limited:

Magnis Energy Technologies Ltd. (ASX:MNS) (OTCMKTS:MNSEF) (FRA:U1P) is involved in and has strategic investments in several aspects of the electrification supply chain including manufacturing of green credentialed lithium-ion battery cells, leading edge battery technology and high quality, high performance anode materials. The company's vision is to enable, support and accelerate the green energy transition critical for the adoption of Electric Mobility and Renewable Energy Storage.



Source:
Magnis Energy Technologies Ltd.



Contact:

Frank Poullas Executive Chairman Ph: +61 2 8397 9888 www.magnis.com.au


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Magnis Energy Technologies Ltd.
Bergbau
A12CDJ
AU000000MNS3
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"