Perseus is pleased to announce details of assay results from recent infill drilling on the Mampong deposit at its Edikan Gold Mine in Ghana, West Africa. These assay results represent the initial drilling results from a planned 5,560m infill drilling program which to date, is approximately half complete. The Mampong deposit is located between 700m [...]
Perseus will be releasing its audited Consolidated Financial Report for the twelve months ending 30 June 2014 today. The Consolidated Financial Report and Management Discussion & Analysis are available for download from www.perseusmining.com, www.asx.com.au and www.sedar.com. The key points relating to the financial result are as follows: A loss of [...]
Perseus reports that following an infill drilling programme on the Edikan Gold Mine mining leases in Ghana in the period up to June 2014, and after adjusting key assumptions to reflect actual results to date, Mineral Resource estimates have been updated by independent consultant, RungePincockMinarco in accordance with the JORC Code - 2012 Edition [...]
Perseus Mining reports on its activities for the three month period ended June 30, 2014. An executive summary is provided below. However, full details of activities in the June Quarter, including reconciled production and all-in site cash costs, are included in the Company's June 2014 Quarterly Activity Report released to the market on July 29 [...]
Perseus Mining Limited is hosting a conference call to discuss the Quarterly Activity Report for the period ended June 30, 2014, which is anticipated for release around 8.30am AEST on Tuesday July 29, 2014. Conference call details are as follows:
Perseus Mining is very pleased to advise that following our announcement on June 13, 2014 documenting the receipt of an initial GH¢20.0M (USD6.7M) partial payment of the outstanding VAT debt owed to the Company by the Government of Ghana, the two further payments of GH¢10.0M (USD3.3M) and GH¢ 17.6M (USD5.8M) have been received as scheduled on June [...]
Perseus Mining is pleased to provide details of further high grade gold intercepts recorded during recent drilling on the Bokitsi South Deposit at its Edikan Gold Mine in Ghana, West Africa. Bokitsi South is the first of a number of targets to be drill tested with the aim of identifying high grade mineralisation that can be included in mill feed [...]
Perseus Mining is pleased to provide details of high grade gold intercepts recorded during recent drilling on the Bokitsi South Deposit at its Edikan Gold Mine (EGM) in Ghana, West Africa. (Refer to Figure 1 - Location Map)
Perseus Mining wishes to advise of two recent developments relating to its Edikan Gold Mine in Ghana. On 11 June 2014, Perseus received GH¢20.0M (USD6.7M) as a partial payment of the outstanding VAT debt of GH¢97.5M (USD32.7M) owed to the Company by the Government of Ghana. Based on dialogue with the Government, two further payments of GH¢10.0M [...]
Perseus reports on its activities for the three month period ended 31 March 2014. An executive summary is provided below, however the full report is available for download from www.perseusmining.com, www.asx.com.au and www.sedar.com. Full details of activities in the March Quarter, including reconciled production and all-in site cash costs, will be [...]
Perseus is pleased to advise that ore processing operations resumed at its Edikan Gold Mine in Ghana at approximately 5.00pm GMT on Wednesday April 16, 2014, seven days after a fire occurred in the cyclone nest of the plant while undergoing routine maintenance. Perseus's Managing Director Jeff Quartermaine said that, following a thorough [...]
Perseus advises that at approximately 2.00pm GMT on Wednesday 9 April 2014, there was a fire in the processing plant at the Company's Edikan Gold Mine in Ghana while the plant was shut down for scheduled maintenance. The Company's Emergency Response Team was activated and the fire was brought under control within an hour. The fire caused no [...]