eCobalt Solutions Inc. announces that it has obtained a receipt for the final short form base shelf prospectus from the British Columbia Securities Commission on March 15, 2019 . This is a renewal of the Company's previous base shelf prospectus, a final receipt for which was obtained on January 12, 2017 and which was effective for a period of 25 [...]
eCobalt Solutions Inc. announces that it has filed and obtained a receipt for a preliminary short form base shelf prospectus with the Securities Commissions in each of the provinces of Canada, other than the Province of Quebec. This is a renewal of the Company's previous base shelf prospectus, a final receipt for which was obtained on January 12 [...]
Focus to be placed on securing offtake and finalizing feasibility study while preserving treasury eCobalt Solutions Inc. announces that in response to current cobalt market conditions it is imposing cost control measures throughout the organization to preserve its treasury while it focuses on critical path items needed to bring the Idaho Cobalt [...]
New targeted production rate increases throughput 50% providing robust project economics and resilience to lower cobalt prices eCobalt Solutions Inc. is pleased to provide an update on its Idaho Cobalt Project , located near the town of Salmon in east-central Idaho, in the heart of the historic Idaho Cobalt Belt. The ICP is the only near-term [...]
eCobalt Solutions Inc. is pleased to provide a progress update on its Idaho Cobalt Project , located near the town of Salmon, in the heart of the historic Idaho Cobalt Belt. The ICP remains the only near-term, environmentally permitted primary cobalt deposit in the United States. Following a very busy and productive spring and summer season [...]
eCobalt Solutions Inc. announces that Mr. Paul Farquharson will retire as President, Chief Executive Officer and Director of the Board on October 1, 2018, and will be succeeded by Mr. Michael Callahan as President, CEO and Director of the Board. Mr. Callahan is a strong and experienced executive with extensive operational and public-company [...]
Water Treatment Plant infrastructure and Pond liner near completion; Tailings Waste Storage Facility liner and pipelines in progress; commencing mill foundations eCobalt Solutions Inc. reports that construction continues to advance on time and on budget at its Idaho Cobalt Project , located near the town of Salmon, in the heart of the historic [...]
Metallurgical Testing Confirms Feasibility Level Process Flowsheet for the Cobalt Production Facility eCobalt Solutions Inc. announces the successful completion of pilot-level metallurgical testing for the Company's 100% owned Idaho Cobalt Project , located near the town of Salmon, in the heart of the historic Idaho Cobalt Belt. The ICP remains the [...]
Foundations being laid and construction of Water Treatment Plant commencing eCobalt Solutions Inc. reports that construction continues to advance on time and on budget at its Idaho Cobalt Project , located near the town of Salmon, in the heart of the historic Idaho Cobalt Belt. The ICP remains the sole, near-term environmentally permitted primary [...]
Critical equipment and power delivered to site; pouring of concrete commenced VANCOUVER, July 12, 2018 /CNW/ - eCobalt Solutions Inc. is pleased to provide an update on construction progress at the Company's 100% owned Idaho Cobalt Project , located near the town of Salmon, in the heart of the historic Idaho Cobalt Belt. The ICP remains the sole [...]
VANCOUVER, June 29, 2018 /CNW/ - eCobalt Solutions Inc. announces that all proposed resolutions were passed at its Annual General Meeting , held on June 28, 2018 in Vancouver, Canada. A total of 57,198,371 common shares of the 159,540,586 common shares outstanding were voted, representing 35.85% of the issued and outstanding common shares of [...]
Metallurgical test work indicates ICP ore more amenable to rotary kiln roaster. Project financing advancing successfully. VANCOUVER, June 25, 2018 /CNW/ - eCobalt Solutions Inc. is pleased to provide an update on the status of the Optimized Feasibility Study and on progress of project financing for the Company's 100% owned Idaho Cobalt Project [...]