Telson Mining is pleased to announce that further to its news releases dated December 27, 2019 and February 13, 2020, the Company is seeking a 30 day extension from the date hereof from the TSX-V to close its non-brokered private placement offering of up to of up to 30,000,000 units at a price of C$0.10 per Unit for total proceeds of up to [...]
Telson Mining Corp. is pleased to announce that it has entered into a letter agreement with Trafigura Mexico, which defines the terms under which Trafigura will provide Telson a waiver to certain terms of the Loan Agreements entered into between the companies. Under the terms of the Letter Agreement, Telson acknowledges that it is in default of its [...]
Telson Mining informs shareholders that the Mexican Ministry of Health has proclaimed a national health emergency with an immediate suspension order of all "non-essential" public and private sector business, including mining in order to mitigate the spread and transmission of the COVID-19 virus. The order became effective on its publication date in [...]
Telson Mining Corp. is pleased to provide an update on operations at the Campo Morado mine since it was brought back into production as of January 26, 2020. Since re-him him initiation of production covering the period January 26, 2020 through to February 22, 2020 the Campo Morado mill has produced approximately 3,151 tonnes of zinc concentrates [...]
Telson Mining wishes to inform shareholders that for personal reasons, Jose Antonio Berlanga has resigned his positions as Chief Executive Officer and Member of the Board of Directors of the Company. Telson wishes to thank Senor Berlanga for his past services and dedication to the company wishing him well as he chooses to initially spend more time [...]
Telson Mining Corp. is pleased to announce that it has closed a first tranche of the non-brokered private placement originally announced on December 27, 2019. This first tranche consisted of 19,458,442 units of the Company at a price of $0.10 per unit for gross proceeds of $1,945,844. Each unit is comprised of one common share and one half of one [...]
Telson Mining Corp. is pleased to announce that it has resumed full scale mining and milling operations at its Campo Morado Mine as of January 26th, 2020. The company has re-initiated milling operations at approximately 1750 tonnes per day, intending to increase throughput rate over the coming weeks towards 2000 tonnes per day or more. Underground [...]
Dec 27, 2019 Telson Mining Corp. advises that reactivation activities to bring its Campo Morado mine out of care and maintenance back into production are progressing and anticipates to resume mining and processing activities mid January 2020. After having electrical power restored to the mine site three weeks later than anticipated due to [...]
Receives Default Notice from Nyrstar Vancouver, British Columbia - TheNewswire - October 25, 2019 - Telson Mining Corp. , , ) is pleased to announce that as a result of an improving market price for zinc and improved relations within the local community that it will recommence mining operations at Campo Morado. All necessary steps are being taken [...]
Vancouver, British Columbia - TheNewswire - September 4, 2019 - Telson Mining Corp. , , ) is pleased to announce that it has received conditional approval for a US$12 million medium term loan from an International Investment Bank to finalize construction at Tahuehueto. Having successfully completed technical, financial and commercial due diligence [...]
Vancouver, British Columbia - TheNewswire - August 28, 2019 - Telson Mining Corp. ) is pleased to announce that significant recoveries have been achieved in the first week of processing Tahuehueto pre-production ore at the third party Atocha Toll Mill. Up to August 25 inclusive, just over 2,100 tonnes of concentrate has been processed over a [...]
Vancouver, British Columbia - TheNewswire - August 16, 2019 - Telson Mining Corp. ) is pleased to announce that ore shipments from its flagship Tahuehueto Gold Mine under construction are underway for delivery to the Atocha Toll Mill for processing scheduled to begin early next week. Approximately 5,000 tonnes of Tahuehueto ore at a cut-off grade [...]