Symbol: LGO (TSX.V)www.largoresources.com TORONTO, May 20, 2014 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to announce that it will host an inauguration ceremony at the Maracás Vanadium Project in Bahia, Brazil this coming Wednesday, the 21st of May. High level officials from the Federal Government of Brazil, the state of [...]
Symbol: LGO (TSX.V) www.largoresources.com TORONTO, May 16, 2014 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to announce that it has begun the warming of the kiln at the Maracas Vanadium project in Bahia, Brazil. The warming of the kiln signals the conclusion of the commissioning process at the facility. Once the kiln has [...]
Symbol: LGO (TSX.V)www.largoresources.com TORONTO, May 15, 2014 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") wishes to inform shareholders that it has alerted IIROC's Market Surveillance division about irregular trading patterns in Largo's securities which the Company has observed recently. About Largo Largo is a growing strategic [...]
Symbol: LGO (TSX.V) Construction 99.8% complete Commissioning complete or underway on all systems Largo adds senior vanadium technical manager to operations team TORONTO, April 10, 2014 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to provide an operational update for its 100% owned Maracas Vanadium Project (the "Project [...]
Symbol: LGO (TSX.V) www.largoresources.com TORONTO, March 18, 2014 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to announce that commissioning of the kiln is currently underway at the Maracas Vanadium Project (the "Project"). All systems at the Project are expected to be mechanically complete and in commissioning by the [...]
Symbol: LGO (TSX.V) www.largoresources.com Crushing System Fully Operational with 18,000 Tonnes Crushed and Stockpiled Grinding and Beneficiation System Commissioning is Underway and Vanadium Pentoxide Concentrate Production has Commenced Evaporation System Mechanically Completed and Commissioning Initiated Kiln & Cooler Sections [...]
/NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR RELEASE, PUBLICATION, DISTRIBUTION OR DISSEMINATION IN THE UNITED STATES/ TORONTO, Dec. 13, 2013 /CNW/ - Largo Resources Ltd. (TSX-V:LGO) ("Largo" or the "Company") is pleased to announce that it has closed its previously announced non-brokered private placement of common shares (the [...]
Symbol: LGO (TSX.V) TORONTO, Nov. 29, 2013 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to provide an updated budget estimate ("Budget" or "CAPEX") for mechanical completion of its Maracas Vanadium Project (the "Project") in Bahia, Brazil. The current budget forecast for mechanical completion of the project is USD $248 [...]
/NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR RELEASE, PUBLICATION, DISTRIBUTION OR DISSEMINATION IN THE UNITED STATES/ TORONTO, Nov. 29, 2013 /CNW/ - Largo Resources Ltd. (TSXV:LGO) ("Largo" or the "Company") announced today a C$17 million non-brokered private placement of common shares (the "Offering") at a price of C$0.20 per [...]
Significant Progress on Mechanical and Electrical Construction Activities Kiln Rollers on Site and Kiln Erection on track for Q1 Commissioning Crushing System Commissioning Successful and Ongoing Symbol: LGO (TSX.V) TORONTO, Nov. 26, 2013 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to provide the following operational [...]
Symbol: LGO (TSX.V) www.largoresources.com TORONTO, Nov. 11, 2013 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to announce the appointment of Mr. Michael Mutchler to the position of Chief Operating Officer ("COO"). Mr. Michael Mutchler is a Mining Engineer with over 33 years' experience in mining, including: open pit and [...]
Symbol: LGO (TSX.V) TORONTO, Oct. 21, 2013 /CNW/ - Largo Resources Ltd. ("Largo" or the "Company") is pleased to announce that the installation of the main power line to the Company's Maracás Vanadium Project ("the Project") in Bahia Brazil has concluded. The 11 megawatt, 86 kilometer electrical power line is now connected to the national grid and is supplying power for Project operations. With main power line installation now complete, full commissioning of the crushing system will commence shortly. Likewise, testing and pre-commissioning of other completed system areas can now begin. ... [...]