- Intersects 219.0m @ 1.65g/t Gold, including 8.65m @ 6.14g/t Gold.

Also 154.0m @ 1.31g/t Gold, including 18.3m @ 2.51g/t Gold

TORONTO, March 14, 2012 /CNW/ - Volta Resources Inc. ('Volta Resources' or the 'Company')

announces the results from the last six core drill holes from the Phase 3 program at its Kiaka Gold Project in Burkina Faso. Phase 3 comprised approximately 50,000m of drilling being undertaken to extend resources in the Central Area, to follow up positive results in the South Area, to test several more ground geophysical targets and undertake scout drilling on regional targets on the Kiaka property (see News Release of 13 October 2011).

The reported holes, comprising a total of 3,837.26m, were drilled across the central and southern parts of the Kiaka Main Zone (KMZ) orebody. They aimed at extending the resources at depth. All holes, except KDH338 (oriented N315°E), were oriented N135°E and drilled with an inclination of -60°.

All the holes clearly confirm the continuity of wide mineralization at depth, often exceeding 1.0g/t Au over considerable widths. These holes have  extended the mineralization in the Central Area to vertical depths ranging between 425m and 500m.  These holes complete Phase 3 drilling for the Kiaka Central Area and will now be included with the rest of the results in updating the current NI43-101 resource currently being finalised by SRK Consulting UK (Cardiff).

The highlights from the reported drillholes include :



217.20m @ 1.07g/t Au, including 7.00m @ 3.07g/t
-- KDH338 : Au.

17.00m @ 1.35g/t Au, including 3.05m @ 1.65g/t Au
-- KDH339 : AND

219.00m @ 1.65g/t Au, including 8.65m @ 6.14g/t Au
-- KDH339 : and 17.00m @ 4.81g/t Au.

29.25m @ 1.37g/t Au, including 5.00m @ 5.56g/t Au
-- KDH341 : AND

59.80m @ 1.02g/t Au, including 4.40m @ 5.60g/t Au
-- KDH341 : AND

-- KDH341 : 118.00m @ 0.76g/t Au, including 23.50m @ 1.69g/t Au.

104.00m @1.12g/t Au, including 6.00m @ 6.84g/t Au
-- KDH343 : AND

-- KDH343 : 154.00m @ 1.31g/t Au, including 18.30m @ 2.51g/t Au.



Results for the holes are highlighted in Table 1 and in locations shown in Figure 1. Analyses of the Volta samples were undertaken by fire assay on a 50g charge at ALS Chemex Laboratories in Ouagadougou. Volta's sampling and assay procedures included rigorous QA/QC elements that employed the inclusion of certified standards and blanks.

Table 1: Highlights of gold intersections for the reported boreholes


_________________________________________________________________________
| SECTION| BHID | FROM | TO |INTERVAL| Au | COMMENTS |
|_____________|______|______|______|________|_____|_______________________|
| | | (m) | (m) | (m) |(g/t)| |
|_____________|______|______|______|________|_____|_______________________|
| 5150N |KDH327|234.00|244.95| 10.95 |0.78 | |
| |______|______|______|________|_____|_______________________|
| |AND |266.00|282.00| 16.00 |0.86 | |
| |______|______|______|________|_____|_______________________|
| | INCL|266.00|270.00| 4.00 |1.51 | |
| |______|______|______|________|_____|_______________________|
| | INCL|275.00|278.00| 3.00 |1.54 | |
| |______|______|______|________|_____|_______________________|
| |AND |298.00|405.00| 107.00 |0.63 | |
| |______|______|______|________|_____|_______________________|
| | INCL|327.00|332.00| 5.00 |2.23 | |
| |______|______|______|________|_____|_______________________|
| |AND |428.00|439.00| 11.00 |1.57 | |
| |______|______|______|________|_____|_______________________|
| | INCL|429.00|436.00| 7.00 |2.19 | |
| |______|______|______|________|_____|_______________________|
| |AND |445.00|461.50| 16.50 |0.79 | |
| |______|______|______|________|_____|_______________________|
| | INCL|450.00|456.00| 6.00 |1.49 | |
|_____________|______|______|______|________|_____|_______________________|
|5350N |KDH338|313.80|531.00| 217.20 |1.07 |463.0-464.0m=10.85g/t; |
| | | | | | |518.35-519.00m=35.9g/t |
| |______|______|______|________|_____|_______________________|
| | INCL|324.00|327.00| 3.00 |1.53 | |
| |______|______|______|________|_____|_______________________|
| | INCL|343.00|355.00| 12.00 |1.04 | |
| |______|______|______|________|_____|_______________________|
| | INCL|368.00|388.00| 20.00 |1.25 | |
| |______|______|______|________|_____|_______________________|
| | INCL|394.30|398.70| 4.40 |1.93 | |
| |______|______|______|________|_____|_______________________|
| | INCL|403.35|412.15| 8.80 |1.43 | |
| |______|______|______|________|_____|_______________________|
| | INCL|416.00|425.00| 9.00 |1.27 | |
| |______|______|______|________|_____|_______________________|
| | INCL|428.40|432.00| 3.60 |1.30 | |
| |______|______|______|________|_____|_______________________|
| | INCL|443.00|458.00| 15.00 |1.26 | |
| |______|______|______|________|_____|_______________________|
| | INCL|461.00|468.00| 7.00 |3.07 | |
| |______|______|______|________|_____|_______________________|
| | INCL|472.00|481.00| 9.00 |1.75 | |
| |______|______|______|________|_____|_______________________|
| | INCL|485.00|494.00| 9.00 |1.24 | |
| |______|______|______|________|_____|_______________________|
| |AND |593.00|596.00| 3.00 |1.24 | |
|_____________|______|______|______|________|_____|_______________________|
|5300N |KDH339|305.00|322.00| 17.00 |1.35 |319.0-320.0m=16.55g/t |
| | | | | | |Au |
| |______|______|______|________|_____|_______________________|
| | INCL|316.95|320.00| 3.05 |5.92 | |
| |______|______|______|________|_____|_______________________|
| |AND |350.00|569.00| 219.00 |1.65 |393.35-394.00m=31.3g/t |
| | | | | | |Au |
| |______|______|______|________|_____|_______________________|
| | INCL|359.00|390.00| 31.00 |2.00 | |
| |______|______|______|________|_____|_______________________|
| | INCL|392.35|401.00| 8.65 |6.14 |395.00-396.00m=23.00g/t|
| | | | | | |Au |
| |______|______|______|________|_____|_______________________|
| | INCL|409.00|417.00| 8.00 |2.05 | |
| |______|______|______|________|_____|_______________________|
| | INCL|424.00|429.15| 5.15 |1.12 | |
| |______|______|______|________|_____|_______________________|
| | INCL|435.00|443.00| 8.00 |1.83 | |
| |______|______|______|________|_____|_______________________|
| | INCL|445.00|462.00| 17.00 |4.81 |441.00-462.00m=21.00g/t|
| | | | | | |Au |
| |______|______|______|________|_____|_______________________|
| | INCL|464.20|471.00| 6.80 |1.38 | |
| |______|______|______|________|_____|_______________________|
| | INCL|488.00|492.00| 4.00 |1.13 | |
| |______|______|______|________|_____|_______________________|
| | INCL|497.00|505.00| 8.00 |1.90 | |
| |______|______|______|________|_____|_______________________|
| | INCL|509.00|525.20| 16.20 |2.70 | |
| |______|______|______|________|_____|_______________________|
| | INCL|543.00|558.00| 15.00 |1.06 | |
| |______|______|______|________|_____|_______________________|
| |AND |579.00|599.00| 20.00 |0.54 | |
|_____________|______|______|______|________|_____|_______________________|
|5375N |KDH340|259.00|289.00| 30.00 |0.52 | |
| |______|______|______|________|_____|_______________________|
| |AND |303.00|324.00| 21.00 |0.66 | |
| |______|______|______|________|_____|_______________________|
| | INCL|303.00|308.00| 5.00 |1.66 | |
| |______|______|______|________|_____|_______________________|
| |AND |402.00|411.00| 9.00 |1.28 | |
| |______|______|______|________|_____|_______________________|
| | INCL|402.00|405.00| 3.00 |2.17 | |
| |______|______|______|________|_____|_______________________|
| |AND |456.00|475.00| 19.00 |0.66 | |
| |______|______|______|________|_____|_______________________|
| |AND |490.00|508.00| 18.00 |0.99 | |
| |______|______|______|________|_____|_______________________|
| | INCL|492.00|499.00| 7.00 |1.01 | |
| |______|______|______|________|_____|_______________________|
| | INCL|502.00|508.00| 6.00 |1.44 | |
| |______|______|______|________|_____|_______________________|
| |AND |514.00|554.00| 40.00 |0.72 | |
| |______|______|______|________|_____|_______________________|
| | INCL|540.00|544.00| 4.00 |1.95 | |
| |______|______|______|________|_____|_______________________|
| | INCL|549.00|553.00| 4.00 |1.30 | |
| |______|______|______|________|_____|_______________________|
| |AND |583.00|638.15| 55.15 |0.76 | |
| |______|______|______|________|_____|_______________________|
| | INCL|604.00|608.20| 4.20 |2.77 | |
| |______|______|______|________|_____|_______________________|
| | INCL|612.00|615.00| 3.00 |2.82 | |
|_____________|______|______|______|________|_____|_______________________|
|5425N |KDH341|212.00|241.25| 29.25 |1.37 | |
| |______|______|______|________|_____|_______________________|
| | INCL|225.00|230.00| 5.00 |5.56 | |
| |______|______|______|________|_____|_______________________|
| |AND |268.00|274.00| 6.00 |1.52 | |
| |______|______|______|________|_____|_______________________|
| |AND |280.70|284.00| 3.30 |1.26 | |
| |______|______|______|________|_____|_______________________|
| |AND |292.30|331.60| 39.30 |0.76 | |
| |______|______|______|________|_____|_______________________|
| | INCL|297.00|307.00| 10.00 |1.48 | |
| |______|______|______|________|_____|_______________________|
| | INCL|328.00|331.60| 3.60 |1.24 | |
| |______|______|______|________|_____|_______________________|
| |AND |383.00|410.45| 27.45 |0.90 | |
| |______|______|______|________|_____|_______________________|
| | INCL|394.00|397.00| 3.00 |3.60 | |
| |______|______|______|________|_____|_______________________|
| |AND |459.00|518.80| 59.80 |1.02 |488.90-489.40m=42.4g/t |
| | | | | | |Au |
| |______|______|______|________|_____|_______________________|
| | INCL|485.00|489.40| 4.40 |5.60 | |
| |______|______|______|________|_____|_______________________|
| | INCL|503.00|509.00| 6.00 |1.22 | |
| |______|______|______|________|_____|_______________________|
| |AND |535.00|653.00| 118.00 |0.76 | |
| |______|______|______|________|_____|_______________________|
| | INCL|554.00|559.00| 5.00 |1.37 | |
| |______|______|______|________|_____|_______________________|
| | INCL|562.00|568.00| 6.00 |1.21 | |
| |______|______|______|________|_____|_______________________|
| | INCL|578.50|602.00| 23.50 |1.69 | |
| |______|______|______|________|_____|_______________________|
| | INCL|606.00|610.00| 4.00 |1.09 | |
|_____________|______|______|______|________|_____|_______________________|
| 5325N |KDH343|149.00|177.00| 28.00 |0.60 | |
| |______|______|______|________|_____|_______________________|
| |AND |227.00|331.00| 104.00 |1.12 |245.00246.00m=35.80g/t |
| | | | | | |Au; |
| | | | | | |259.00-260.00m=10.30g/t|
| | | | | | |Au |
| |______|______|______|________|_____|_______________________|
| | INCL|245.00|251.00| 6.00 |6.84 | |
| |______|______|______|________|_____|_______________________|
| | INCL|315.00|318.00| 3.00 |3.43 | |
| |______|______|______|________|_____|_______________________|
| |AND |438.00|592.00| 154.00 |1.31 |569.00-570.00m=14.40g/t|
| | | | | | |Au |
| |______|______|______|________|_____|_______________________|
| | INCL|443.00|470.00| 27.00 |1.38 | |
| |______|______|______|________|_____|_______________________|
| | INCL|481.00|493.00| 12.00 |1.04 | |
| |______|______|______|________|_____|_______________________|
| | INCL|495.00|500.00| 5.00 |1.36 | |
| |______|______|______|________|_____|_______________________|
| | INCL|506.20|515.00| 8.80 |2.22 | |
| |______|______|______|________|_____|_______________________|
| | INCL|519.00|532.00| 13.00 |2.53 | |
| |______|______|______|________|_____|_______________________|
| | INCL|553.70|572.00| 18.30 |2.51 | |
| |______|______|______|________|_____|_______________________|
| |AND |606.30|637.85| 31.55 |0.67 | |
| |______|______|______|________|_____|_______________________|
| | INCL|614.00|620.00| 6.00 |1.39 | |
|_____________|______|______|______|________|_____|_______________________|


 Notes on Table 1:


1. Intervals are core length; true width is unknown at this time.
2. Intersections are based on a 0.3 g/t gold cut-off with maximum
internal dilution (MID) of 5m for the lower grade mineralization
envelope, except for hole KDH339 (305.0-322.0m and 350.0-569.0m)
where it has been increased to 5.35m and for holes KDH341
(535.0-653.0m) and KDH343 (149.0-177.0m and 438.0-592.0m) where it
has been increased to 6m.
3. In order to highlight the continuity of the high grade zone, a 0.8
g/t gold cut-off with maximum internal dilution of 2m has been
used.
4. No top cut has been applied.
5. The intersections listed in the table represent sections of at
least 3m in excess of 1g/t Au and/or sections of at least 10m in
excess of 0.5g/t Au.
6. The intersections represent sections drilled by cored drilling
(see Table 2).
7. The cored drill holes were usually sampled at one meter intervals
and cut in half using a diamond saw. Half-core is archived at the
core storage facility on site while the other half was sent to the
laboratory.
8. Samples were sent to ALS Chemex in Ouagadougou for standard
preparation followed by Fire Assay on a 50g charge.
9. Certified standards were inserted every 15 samples, field
duplicates (in the RC portions) about every 20 and blanks about
every 30 samples. The blanks, certified standards and duplicate
assays confirm that all assays used to compile the intersections
quoted here have passed Volta's rigorous QA/QC checks.

TABLE 2 : Collar coordinates and orientation parameters for the reported boreholes.


____________________________________________________________________
|Section|HoleID|Easting|Northing|Elevation|Depth | Dip | Azimuth |
|_______|______|_______|________|_________|______|_________|_________|
| | | | | (m) | (m) |(degrees)|(degrees)|
|_______|______|_______|________|_________|______|_________|_________|
| 5150N |KDH327|739066 |1289410 | 270.26 |532.80| -60 | 135 |
|_______|______|_______|________|_________|______|_________|_________|
| 5300N |KDH339|739139 |1289553 | 274.40 |601.35| -60 | 135 |
|_______|______|_______|________|_________|______|_________|_________|
| 5325N |KDH343|739122 |1289607 | 278.39 |699.83| -60 | 135 |
|_______|______|_______|________|_________|______|_________|_________|
| 5350N |KDH338|739525 |1289233 | 263.41 |601.40| -60 | 315 |
|_______|______|_______|________|_________|______|_________|_________|
| 5375N |KDH340|739153 |1289639 | 278.24 |701.75| -60 | 135 |
|_______|______|_______|________|_________|______|_________|_________|
| 5425N |KDH341|739191 |1289676 | 277.36 |700.13| -60 | 135 |
|_______|______|_______|________|_________|______|_________|_________|


Under the guidelines of National Instrument 43-101, the qualified person for the Kiaka Gold Project is Mr. Guy Franceschi, Vice President, Exploration for Volta. Mr. Franceschi is a member of the European Federation of Geologists and has reviewed and approved the contents of this news release.

Volta is a mineral exploration company primarily focused on becoming a leader in the identification, acquisition and exploration of gold properties in West Africa. The Company is currently fast-tracking its flagship Kiaka Gold Project, located in Burkina Faso, toward a development decision.

Forward Looking Information Caution:

This press release presents 'forward-looking statements' within the meaning of Canadian securities legislation that involve inherent risks and uncertainties.  Forward-looking statements include, but are not limited to, statements with respect to the future price of gold and other minerals and metals, the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the capital expenditures, costs and timing of the resources, the realization of mineral reserve estimates, the capital expenditures, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, currency exchange rate fluctuations, requirements for additional capital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage.  Generally, these forward-looking statements can be identified by the use of forward looking terminology such as 'plans', 'expects' or 'does not expect', 'is expected', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates' or 'does not anticipate', or 'believes', or variations of such words and phrases or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will be taken', 'occur' or 'be achieved'. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Volta to be materially different from those expressed or implied by such forward looking statements, including but not limited to: risks related to international operations, risks related to the integration of acquisitions; risks related to joint venture operations; actual results of current exploration activities; actual results of current or future reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of gold and other minerals and metals; possible variations in ore reserves, grade or recovery rates; failure of equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; and delays in obtaining governmental approvals or financing or in the completion of development or construction activities.  Although the management and officers of Volta believe that the expectations reflected in such forward-looking statements are based upon reasonable assumptions and have attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.  Volta Resources does not undertake to update any forward-looking statements that are incorporated by reference herein, except in accordance with applicable securities laws.

 

 

SOURCE Volta Resources Inc.

PDF with caption: 'Figure 1: Location of reported drillholes.'. PDF available at: http://stream1.newswire.ca/media/2012/03/14/20120314_C4229_DOC_EN_11098.pdf

Volta Resources Inc.

CONTACT: please refer to our website www.voltaresources.com or contact:



Kevin Bullock, P.Eng., President & CEO

Tel: (647) 388-1842

Fax: (416) 867-2298

Email: kbullock@voltaresources.com



or



AndreasCurkovic, Investor Relations

Tel: (416) 577-9927



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Volta Resources Inc.
Bergbau
-
-
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"