PERTH, WESTERN AUSTRALIA--(Marketwired - March 02, 2015) - Paladin Energy Ltd(TSX: PDN)(ASX: PDN) ("Paladin" or the "Company") wishes to advise that, the centrewell on pre-leach thickener #2 at Langer Heinrich failed, making this unit non-operational and necessitating its isolation from the process. Production now will rely on pre-leach thickener #1, reducing plant performance to around 45% of the production capacity.
Pre-leach thickener #2 is likely to be off-line for 8 to 12 days overall while necessary repairs are undertaken. On this estimate, the likely production loss is expected to be up to 100,000lb U3O8 for this quarter. This will likely impact stated production guidance and any revision of this will be advised once a clearer schedule for restart to full production is determined.
ACN 061 681 098
Contact
For additional information, please contact:
John Borshoff Managing Director/CEO Tel: +61-8-9381-4366 or Mobile: +61-419-912-571 Email: john.borshoff@paladinenergy.com.au
Greg Taylor Investor Relations Contact Tel: +1 905 337-7673 or Mobile: +1 416-605-5120 (Toronto) Email: greg.taylor@paladinenergy.com.au
Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!