Suche
 
Folgen Sie uns auf:

Hastings Technology Metals Ltd.: Half Yearly Report - December 2017

14.03.2018  |  ABN Newswire
Sydney - Hastings Technology Metals Ltd. (ASX:HAS) (FRA:5AM) submit the financial report of the Group consisting of Hastings Technology Metals Ltd. ("Company" or "Hastings") and the entities it controlled during the half-year ended 31 December 2017. In accordance with the provisions of the Corporations Act 2001.

Yangibana Project

JORC Resources

Following the completion of the 2017 exploration drilling programme at the Yangibana Project, an updated JORC Resource estimate was completed by independent consultants Widenbar and Associates Pty Limited. Total Resources now stand at 21.00mt as shown in Table 1 (see link below). Note that resource tonnes in the following tables are rounded to the nearest 100,000 tonnes and rounding errors may appear.

These resources include those within tenements held 100% by Hastings (see Table 2 in link below) and those held in joint venture with Hastings holding a 70% interest (Table 3 in link below).

Definitive Feasibility Study (see ASX announcement dated 28 November 2017)

During the period the Company released the Definitive Feasibility Study (DFS) for the Yangibana Rare Earths Project. The Project will produce a Mixed Rare Earths Carbonate (MREC) rich in Neodymium (Nd) and Praseodymium (Pr), critical materials used in the manufacture of permanent magnets, which are found in electrical components of many new technology products, from electric vehicles, renewable energy wind turbines and electronic consumer products.

The DFS demonstrates attractive economics using conservative price projections for the key rare earths of Nd-Pr which the company anticipates will have solid demand based on the strong trending growth of electric vehicles and wind turbines in particular, as well as other technological innovations. The DFS furthermore demonstrated the technical viability of the Yangibana flow sheet.

The DFS calculations are based on the Maiden JORC Ore Reserves of 5.15 million tonnes at 1.12% Total Rare Earths Oxide (TREO) for the first six years of operations, along with a Production Target for years 7 and 8 based on additional JORC Measured and Indicated Resources. All the Ore Reserves and Mineral Resources included in the DFS lie within tenements owned 100% by Hastings.

The production targets and underlying assumptions have not changed from the date of the release of the DFS on 28 November 2017 to the date of this report.

The Probable Ore Reserves at Bald Hill and Fraser's deposits are based on the JORC Resources shown in Tables 4 and 5 (see link below), that form part of the total resources of 21.00 million tonnes. Apparent discrepancies might appear due to rounding.

Mining by open pits will use conventional drill and blasting methods and it is planned to provide 1.0 million tonnes per annum of ore to the processing plant.

The ore dips at between 10 and 45 degrees and varies in thickness between 1m and 20m at Fraser's and 1m and 30m at Bald Hill, with an average thickness of 4m. The ore zone (ironstone) is visually distinct from the host rock, providing some control for ore identification.

RC grade control drilling will be done on a 10m x 10m grid to control ore delineation.

Selective blasting and mining around the ore zones are designed to remove the hanging-wall as cleanly as possible to expose the ore.

The ore will then be mined to the footwall contact using selective mining. Due to the high value of the ore, a high ore recovery will be the focus of mining. As such, a 50cm skin of dilution will be added to the ore mined to enable a 98% ore recovery assumption.

Pits will be dewatered ahead of mining using bores to provide a dewatered rock mass, with a maximum 8 litres per second pumped from each pit. Stormwater will be managed in pit using sumps and with capacity for pumping up to 10 litres per second in each pit.

Waste from each pit will be stored in adjacent waste dumps. Some of the Bald Hill pit will be backfilled to minimise haulage distances. Mineralised material will be transferred directly to the Run-Of-Mine (ROM) pad or to a low-grade stockpile with the mining trucks (as the distance travelled is reasonably low).

Pit optimisations have been completed to determine the economic mining limits for each deposit. Only Measured and Indicated Resources have been considered for processing. Pits have then been designed in stages to enable higher grades to be targeted and waste extraction to be deferred. Both Bald Hill and Fraser's pits are approximately 125m deep. The main Bald Hill pit is approximately 1,100m long and 600m wide. The Fraser's pit is approximately 600m long and 250m wide. The waste dumps have been located to minimise haulage distances and were constrained by lease boundaries (Bald Hill) and water courses. The Bald Hill dump covers an area of 100 hectares (ha), and the Fraser's dump covers 86ha.

The Company has completed extensive metallurgical testwork culminating in pilot plant tests on a composite sample of material from Bald Hill and Fraser's. This testwork has defined a route comprising crush, grind, flotation, acid bake with water leach and precipitation of a Mixed Rare Earths Concentrate. The key parameters are shown in Table 6 (see link below).

All environmental studies and approvals processing are progressing as required.

Based on the resources in Tables 1 and 2 (see link below) and the Modifying Factors, Snowden has estimated the Probable Ore Reserves as shown in Table 7 (see link below).

68% of the initial 8-year operating life is underpinned by these Ore Reserves. An Additional Production Target of 2.64 million tonnes of plant feed based on Measured and Indicated Resources from Auer, Auer North, Yangibana West and Yangibana deposits is included for the financial evaluation. These deposits were selected as the Mineral Resources in these deposits have been demonstrated, through variability testwork programmes, to be compatible with the process flowsheet developed in the DFS. Preliminary modifying factors were applied during a pit optimisation of the Mineral Resources to develop the Additional Production Target tonnage and subsequently, a mining schedule was developed from the optimised pits and used in the financial evaluation of the project.

The processing route commences with comminution and beneficiation, resulting in a beneficiated concentrate upgrade by 20 times from the ROM ore, as demonstrated through the DFS, to a 25% TREO concentrate.

This concentrate is further processed downstream through a hydrometallurgical process that involves acid bake, water leaching, impurity removal and precipitation to produce up to 15,000 tpa of MREC. The MREC will contain up to 3,400 tpa of neodymium oxide (Nd2O3)+praseodymium oxide (Pr6O11). Hastings will sell this Nd2O3+Pr6O11 rich MREC to rare earths oxides separators or other customers further along the rare earths supply chain.

The Project is estimated to generate annual sales revenue of A$379 million, a nominal after tax NPV of A$466 million (discount rate of 8%), an Internal Rate of Return (IRR) of 78% and a 2.3-year payback (average over the 8 years from first draw down) as shown in Table 8 (see link below).

Revenue streams are highly dependent on Nd-Pr prices as these account for 85-90% of projected revenue.

The Company will continue to work on identifying areas where capital expenditure can be further reduced. Significant gains have been achieved on operating expenses, with a reduction of 30% achieved from the PFS. With estimated annual operating expenses at A$142 million per year, the average operating cost for the project is A$17.0/kg TREO (US$12.8/kg), including all fixed and variable costs.

The DFS financial model assumes an average long-term US$/A$ exchange rate of US$0.75 and price forecasts from 2017 to 2027 for rare earths prices from Argus Media, an independent provider of price information, market data and business intelligence for the global resource industry. Hastings anticipates an increase in some of the key rare earths prices, especially Nd-Pr over the next decade due to the strong demand for permanent magnets arising from the growth in electric vehicles. The price rises seen in 2017 demonstrate that the Chinese authorities are having a degree of success in shutting down illegal production in China and Hastings expects the emphasis on sustainable production to continue in China and be supportive of Nd-Pr prices.

Native Title Agreement

In November 2017 the Company signed a Native Title Agreement (NTA) with the Thiin-Mah Warriyangka, Tharrkari and Jiwarli People (TMWTJ People) in respect of the Yangibana Project. The Agreement covers the entire 650km2 of the Yangibana project area.

Commercial

The strengthening in Neodymium (Nd) and Praseodymium (Pr) prices (+42% and +39% respectively year-on-year) and the signing of three offtake Memorandum of Understanding (MOU) agreements with three Chinese rare earth producers provide confidence in the successful development of the Yangibana Rare Earths Project.

The three MOUs signed to date represent approximately 40% of the planned MREC (Mixed Rare Earth Carbonate) annual production from Yangibana.

China further continued to fuel excitement around the announcement of electric vehicle (EV) developments. Chinese authorities hinted of policy changes in early September 2017, with the intention of banning fossil-fuel vehicles. This follows similar policy announcements made by India, Norway, France and the United Kingdom.

Vehicle manufacturers also made encouraging announcements regarding EV targets. Volkswagen will spend EUR 20 billion in R & D to develop electric vehicles. VW aims to roll out 80 EVs models across all its brands by 2025.

Given both policy and manufacturer announcements, the International Energy Agency predicts that by 2030 the stock of EVs on the road globally will total between 160 to 200 million, an almost 100 times increase of the EV stock today. These developments will drive the robust support in demand for Nd and Pr well beyond 2030.

Corporate

Capital Raising

The Company raised $21.5 million during the period with the issue of 139,021,512 shares. This included 51,046,512 at 8.6 cents per share on completion of the share purchase plan and 81,125,000 shares at 20 cents per share through a share placement.

Directors and Management

The Company appointed two new directors during the period, Guy Robertson on 31 July 2017 and Aris Stamoulis on 4 October 2017.

Mr Anthony Ho resigned on 29 November 2017. Mr Ho had previously served as the Company's Chairman and Chairman of the audit committee. The Board is appreciative of Mr Ho's contribution to the Company.

TERMINOLOGY USED IN THIS REPORT

Total Rare Earths Oxides, TREO, is the sum of the oxides of the light rare earth elements lanthanum (La), cerium (Ce), praseodymium (Pr), neodymium (Nd), and samarium (Sm) and the heavy rare earth elements europium (Eu), gadolinium (Gd), terbium (Tb), dysprosium (Dy), holmium (Ho), erbium (Er), thulium (Tm), ytterbium (Yb), lutetium (Lu), and yttrium (Y).

To view the full report with tables and figures, please visit:
http://abnnewswire.net/lnk/867M42O5



About Hastings Technology Metals Ltd:

Hastings Technology Metals Ltd. (ASX:HAS) (FRA:5AM) is currently developing a rare earths mine and processing plant at Yangibana in the Gascoyne Region of Western Australia. The processing plant is anticipated to commence production of MREC in late 2019. Hastings has completed both beneficiation and hydrometallurgy pilot plants, in the process producing MREC samples which are high in neodymium and praseodymium content. These are critical materials for the production of permanent magnets and other technology applications. The MREC will be capable of being further separated and refined to produce a number of individual rare earth oxides outside of Australia. Hastings estimates an annual production quantity of 15,000 tonnes of MREC¹ which it will sell to offtake partners globally.



Contact:

Hastings Technology Metals Ltd.
Charles Lew Executive Chairman
T: +65-9790-9008

Guy Robertson Finance Director
T: +61-9078-7674

Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Hastings Technology Metals Ltd.
Bergbau
A1H79R
AU000000HAS0
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"