Brisbane - Sayona Mining Ltd. (ASX:SYA) (OTCMKTS:DMNXF) ("Sayona" or the "Company") is pleased to report the following update on the pilot plant program underway at SGS Lakefield for the Authier Lithium Project.

The Company has completed the batch and locked cycle phase of the pilot program which had the aim of establishing the optimal conditions for the continuous pilot plant program. The pilot plant operations have now commenced.

During batch and locked cycle testing, the Company has been able to achieve concentrate grades of 6% at metallurgical recoveries of 80%.

Approximately five tonnes of mineralised pegmatite will be processed through the pilot plant. The plant will operate for a minimum of 100 hours at a feed rate of 50 kilogram per hour. The pilot program involved stage-crushing the ore to -3.35mm (see Figure 1 in link below). The crushed ore then passes through a grinding mill, cyclones for de-sliming, magnetic separation for iron removal, mica and spodumene flotation (see Figure 2 and 3 in link below).

The objectives of the pilot plant program include:

- Confirm the flowsheet and process parameters for concentrate production;

- Produce engineering data for equipment sizing and plant design; and

- Generate ~500 kg of spodumene concentrate for downstream testing and marketing purposes.

The results of the pilot program are expected to be available by the end of April and will be incorporated into the Definitive Feasibility Study ("DFS") which will be completed during Q2 2018. On completion of the pilot program, optimisation work will continue with the objective of maximising metallurgical recoveries and de-risking the metallurgical performance of the full-scale operations.

SGS Canada Inc. has considerable experience in developing spodumene concentration flowsheets. Over the past 10 years, SGS has operated pilot plants for several North American hard rock lithium deposits.

To view figures, please visit:
http://abnnewswire.net/lnk/82RJ356F



About Sayona Mining Ltd:

Sayona Mining Ltd. (ASX:SYA) (OTCMKTS:DMNXF) is an Australian-based, ASX-listed (SYA) company focused on sourcing and developing the raw materials required to construct lithium-ion batteries for use in the rapidly growing new and green technology sectors. Sayona’s primary objective is developing the Authier lithium project in Quebec, Canada. Authier is an advanced, near term development project, construction forecast to commence in the second half of 2018 and first production in late 2019. Please visit us as at www.sayonamining.com.au



Contact:

Sayona Mining Ltd.
Corey Nolan Chief Executive Officer
Phone: +61-7-3369-7058
Email: info@sayonamining.com.au
www.sayonamining.com.au

Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Sayona Mining Ltd.
Bergbau
A1W2HT
AU000000SYA5
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"