TORONTO, August 26, 2020 - Gratomic Inc. ("GRAT" or the "Company") (TSXV:GRAT)(OTC PINK:CBULF)(FRANKFURT:CB81) (WKN:A143MR) wishes to announce that its anticipated custom equipment order from China has been safely received ahead of schedule and is currently on site at the Walvis Bay Port in Namibia. This equipment is required for the completion of its Aukam Graphite Mine processing plant construction.

The various components including thickener tanks, cyclone, filter press and chipper, rotary dryer and various additional pieces required for facility completion will be inspected, loaded, and shipped to the Aukam property via trucking service upon clearing customs.

The early arrival has no impact on the Company's prior construction schedule as preparations are currently meeting Gratomic's previously scheduled timelines.

About Gratomic Inc.

Gratomic is a materials company focused on mine to market commercialization of graphite products and components for a range of mass market products. The Company currently holds two off-take purchase agreements for graphite product sourced from the Aukam facility. One agreement is with TODAQ and the other is with Phu Sumika. The Company is listed on the TSX Venture Exchange under the symbol GRAT.

For more information: visit the website at www.gratomic.ca or contact:

Arno Brand at abrand@gratomic.ca or 416 561-4095

"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."

FORWARD LOOKING STATEMENTS:

This press release contains forward-looking statements, which relate to future events or future performance and reflect management's current expectations and assumptions. Such forward-looking statements reflect management's current beliefs and are based on assumptions made by and information currently available to the Company. Investors are cautioned that these forward-looking statements are neither promises nor guarantees and are subject to risks and uncertainties that may cause future results to differ materially from those expected. These forward-looking statements are made as of the date hereof and, except as required under applicable securities legislation, the Company does not assume any obligation to update or revise them to reflect new events or circumstances. All of the forward-looking statements made in this press release are qualified by these cautionary statements and by those made in our filings with SEDAR in Canada (available at www.sedar.com).

SOURCE: Gratomic Inc.



View source version on accesswire.com:
https://www.accesswire.com/603412/Early-Arrival-of-Equipment-from-China-Slated-for-Aukam-Processing-Plant-Completion


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Gratomic Inc.
Bergbau
A2PWQP
CA38900X2077
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"