Austral Resources Australia Ltd: Operational and Strategic Update
Highlights
- Austral is on track to produce 10,000tpa from its Anthill Mine by FY23 despite initial operational delays in production and processing.
- Mining and grade control to date, has confirmed the Resource model tonnage estimates are within 2% of the contained metal value.
- Mining is ahead of schedule by 680,000 BCM's, representing a 12% increase on the original mining schedule.
- Road Haulage is on track and within 3% of the original haulage schedule tonnage.
- Drill and Blast program is 11% ahead of schedule.
Operations
Whilst copper cathode production was below our initial forecast, mining remains ahead of schedule with a total of 6,485,777 BCM mined, representing a 12% increase on the planned mining schedule of 5,806,912 BCM.
Production has also been impacted by the ongoing effects of COVID-19 related staff absenteeism and lengthy interruptions in our supply chain.
Following some initial down time issues with the crushing and stacking infrastructure, post an extensive refurbishment campaign we have now achieved a steady state crushing and stacking operation having achieved a daily average of 6,900t in the past 7 days, compared to the modelled 5,000t per day.
A significant mid-year rain event which recorded more than 80mm of rain impacted production, processing and stacking. The rain caused delays in processing with the main issue being contaminates and solids in the copper processing solution.
Of importance is that Austral, in partnership with Thiess, have pushed ahead and increased the mining schedule to de-risk the mining operation in anticipation of an extended wet season.
Exploration
As announced to the market on 28 July 2022, Austral Resources is continuing with the exploration drilling campaign. Diamond drilling is currently underway at the Lady Colleen prospect and assay results are expected in the coming weeks.
Austral's Managing Director and CEO, Dan Jauncey, commented:
"Austral's copper cathode production estimate has been pushed back following the delays we have incurred. The key takeaway is we are still on track to produce 10,000 tpa for FY23. Mining is ahead of schedule by 12%. Haulage is within 2% of the original haulage schedule and our ROM pads are at full capacity with ore waiting to be crushed and leached. We will endeavour to make this production up over the next 12 months.
"We are on track to produce over 1,000t of copper cathode per month this year, albeit later than originally expected.
"Off the back of our recent equity raise, Austral can fast track our drilling campaign, focusing on the areas in and around Anthill, continue drilling around our multiple target areas including Lady Colleen which has assay results imminent, and focus on finalising our binding joint-venture exploration agreement with Glencore.
"We look forward to updating the market with further developments over the coming weeks."
About Austral Resources Australia Ltd:
Austral Resources Australia Ltd. (ASX:AR1) is a copper cathode producer operating in the Mt Isa region, Queensland, Australia. Its Mt Kelly copper oxide heap leach and solvent extraction/electrowinning (SXEW) plant has a nameplate capacity of 30,000tpa of copper cathode. Austral is developing its Anthill oxide copper mine which has an Ore Reserve of 5.06Mt at 0.94% Cu. The Company expects to produce 40,000t of copper cathode over a four-year period from mid-2022.
Austral owns a significant copper inventory with a JORC compliant Mineral Resource Estimate of 60Mt at 0.7% Cu and 1,940km2 of highly prospective exploration tenure in the heart of the Mt Isa district, a world class copper and base metals province. The Company is implementing an intensive exploration and development programme designed to extend the life of mine and increase then review options to commercialise its copper resources.
Source:
Austral Resources Australia Ltd.