Suche
 
Folgen Sie uns auf:

Uranium Energy Corp Reports S-K 1300 Initial Assessment and Economic Study for the Alto Paraná Titanium Project

13.11.2023  |  CNW

CORPUS CHRISTI, Nov. 13, 2023 - Uranium Energy Corp. (NYSE American: UEC), the "Company" or "UEC") is pleased to announce that it has filed an Initial Assessment Technical Report Summary ("TRS") in accordance with Item 1302 of Regulation S-K ("S-K 1300") on EDGAR disclosing Mineral Resources and an economic assessment for the Company's 100% owned Alto Paraná Titanium Project located in Paraguay (the "Project" or the "Alto Paraná Project").

Key Highlights

  • Alto Paraná Titanium Project is a world-class project with a combined Regional Resource of 3.6 billion tonnes, grading at 7.3% TiO2.
  • The TRS and economic assessment considered two scenarios using Inferred and Indicated Resources:

1. NPV8 of $419 million and a 21% post-tax IRR, utilizing less than 0.2% of the Regional Resource per annum; and
2. NPV8 of $1.55 billion and a 25% post-tax IRR, utilizing less than 0.7% of the Regional Resource per annum.

  • The TRS and economic assessment was co-authored by TZ Minerals International Pty Ltd (TZMI), a global, independent consulting and publishing company which specialises in the mineral sands, titanium dioxide and coatings industries.
  • UEC will commence a global strategic review process to determine the best value-enhancing option for Alto Paraná.

Amir Adnani, UEC President and CEO, stated: "UEC is a uranium focused company and through our presence and uranium exploration activities in Paraguay since 2012 we identified a unique opportunity to acquire the world-class Alto Paraná Titanium Project in 2017 for a nominal investment.

We are delighted to present an initial economic evaluation of the Project that provides a pathway forward in unlocking its substantial value. The study confirms Alto Paraná as one of the highest grade and largest known ilmenite deposits on the globe with compelling economics.

We are looking forward to the next steps in our monetization strategy and plan to retain a financial advisor to conduct a global strategic review, with the aim of maximizing the value of this world-class project for UEC shareholders, stakeholders and the country of Paraguay."

Background:
  • Total Alto Paraná Titanium Project Regional Resources are 3.6 billion tonnes grading at 7.3% TiO2 (titanium dioxide) with an average thickness of 6.3 meters and no overburden (see Table 1 below).
  • Following the acquisition of the Project in 2017 from CIC Resources, UEC has undertaken additional delineation drilling during 2019 through 2023 and further process test work to increase the confidence level of the resource and process.
  • UEC has completed this S-K 1300 TRS and economic assessment with the team at TZ Minerals International Pty Ltd. ("TZMI"), a global, independent consultant which specialises in mineral sands, titanium dioxide and coatings industries. TZMI fulfilled the role of Qualified Person under S-K 1300.
  • The Alto Paraná Titanium Project Initial Assessment examined a base case and a more tentative stretch case for production of high titania slag and high purity pig iron.
  • The base case design (~150,000 tonnes per annum ("tpa") high titania slag and ~100,000 tpa high purity pig iron), using Inferred and Indicated Resources produced the following results:
    • $419 million post-tax net present value ("NPV") using an 8% discount rate;
    • A 21% internal rate of return ("IRR");
    • Startup capital expenditures of $338 million and real after-tax payback of 4.7 years;
    • An average life of mine operating cost of $712 per tonne of slag before pig iron credit over the 23 years modelled;
    • Average life of mine annual revenue of $200 million;
    • A revenue to cash cost ratio of 2.2; and
    • Utilizing less than 0.2% of the available Regional Resource per annum.
  • The stretch production case design (~500,000 tpa high titania slag and ~320,000 tpa high purity pig iron), examined in less detail and with less certainty regarding the resource and market availability, using Inferred and Indicated Resources produced the following outcomes:
    • $1.55 billion post-tax NPV using an 8% discount rate;
    • A 25% IRR;
    • Startup capital expenditures of $918 million and real after-tax payback of 4.2 years;
    • An average life of mine operating cost of $681 per tonne of slag before pig iron credit over the 23 years modelled;
    • Average life of mine annual revenue of $652 million;
    • A revenue to cash cost ratio of 2.3; and
    • Utilizing less than 0.7% of the available Regional Resource per annum.
  • The Project is planned to be powered by low-cost renewable power from the world's second largest hydro-electric power infrastructure (Itaipu), < 25km from the proposed smelter site.
  • The estimated carbon intensity is below 0.6t CO2e/tonne of final product, less than half that of the next lowest ilmenite smelting operation considered in the study.
  • The Project is 100% owned by UEC's wholly owned subsidiary, CIC Resources (Paraguay) Inc., and is located within Eastern Paraguay, near established logistical infrastructure.

Jacob Deysel, UEC VP for Heavy Minerals, leading the Alto Paraná economic study and next steps, stated: "Alto Paraná is a best-in-class titanium Project with substantial resources, relatively low environmental impact, low greenhouse gas footprint, exceptional lifespan, located near supportive infrastructure in a mining friendly jurisdiction and well supported by market fundamentals. This Initial Assessment TRS marks an important step in our efforts to capture the value from this heavy mineral asset in Paraguay. It has upgraded the Alto Paraná resource, refined the technical approach to the development of the Project and the financial assessment shows robust financial returns.

In advancing the project further, we are pleased to employ a dedicated heavy minerals team that includes well-respected experts in the heavy minerals industry, including, Ian Egan (Marketing Consultant) and Colin Rothnie (Geologist) together with specialist consultant, TZ Minerals International Pty Ltd (TZMI). The Project's excellent economic analysis and resources are solid precursors that provide UEC with various options in our strategy to enhance the value of the Project."

About the Alto Paraná Project

The Alto Paraná Project is one of the world's highest-grade and largest ilmenite deposits with a combined Regional Resource of 3.6 billion tonnes grading at 7.3% TiO2. Mineralization occurs at the surface, with an average thickness of 6.3 meters. Future expanded development and mining can benefit from the highly reliable and accessible infrastructure in the area with proximity to a major hydroelectric power source and various bulk commodity transport routes (see Figure 1 below). Prior to UEC's acquisition of the Alto Paraná Project, approximately $25 million was invested in the Project, including pilot testing from mining through to the smelting processes.

As part of the recent Project development, infill drilling has been undertaken in the initial target mining area which has improved the current resource classifications (see Table 1 below). Both in-field and laboratory scale test work were carried out to further improve and simplify the previously proven flowsheet for the Project. The field work and resource estimate were overseen by Colin Rothnie, BSc Hons (Geology), MAusIMM, (201546), employed by UEC as a consulting geologist and a Qualified Person for the TRS. The TRS was co-authored by TZMI, an independent, third-party consulting firm comprised of industry experts, such as professional metallurgists and professional engineers. TZMI professionals fulfill the requirements to be a "Qualified Person" for the purposes of S-K 1300.

Table 1 - UEC's Alto Paraná Resource

Zone (Model)

Resource
category

Volume (Mm3)

Tonnes (Mt)

Ilmenite1,2

Whole rock TiO2

MYNM Regional3, 4

Inferred

2,900

3,500


7.3 %

Block E1 (E1E)

Indicated

28

34

4.9 %

7.5 %

Block A (A5C)

Indicated

30

36

4.8 %

7.7 %

Block A (A5C)4

Inferred

67

80


7.7 %

TOTAL3


3,000

3,600


7.3 %







Notes:

1.

Ilmenite: 'heavy mineral' particles between 45µm and 1mm, denser than 2.8g/cm3 containing an average of 50% TiO2

2.

All grades are expressed as in situ grades.

3.

Estimates for the MYNM Regional Resource and the Total are rounded to two significant figures, as appropriate for Inferred Resources.

4.

On the basis of sampling and comparison assays done to date it is estimated the Inferred Resources contain between 4 and 5% ilmenite.

5.

A cut-off grade of 2% ilmenite has been applied where the ilmenite grade is known, otherwise whole rock TiO? of 5.75%.


Economic Analysis

The TRS demonstrates the potential for the Alto Paraná Project to be a significant high titania slag and high purity pig iron producer which is expected to rank in the first quartile of the TZMI long-term industry revenue to cash cost ratio curve, with exceptional low greenhouse gas emission intensity (see Figure 2 below). Among other matters, it highlights six key areas of refinement over previous studies, being: the resource; the flowsheet; tailings disposal; product marketing; environmental aspects; and financial modelling; with the following results:

  • A base case after-tax IRR of 21% and an NPV after-tax of $419 million using Inferred and Indicated Resources:
    • Initial design production capacity of approximately 150,000 tonnes per annum of high titania slag and 100,000 tonnes per annum of high purity pig iron.
    • An initial mine life of 23 years with potential for significant expansion and extension;
    • Startup capital expenditures of $338 million;
    • A real after-tax payback of 4.7 years;
    • An average life of mine operating cost of $712 per tonne of slag before pig iron credit;
    • Average life of mine annual revenue of $200 million;
    • A revenue to cash cost ratio of 2.2, likely placing it in the first quartile of the TZMI revenue to cash cost ratio curve; and
    • The lowest greenhouse gas emissions per tonne of final products compared to five existing ilmenite smelters considered in the analysis; and
  • The stretch production case using Inferred and Indicated Resources produces significant improved economics with an after-tax IRR of 25% and an NPV after-tax of $1.55 billion.
  • In the base case economic analysis 58% of the resources are Inferred and in the stretch case 86% of the resources are Inferred.
  • The economic assessments are preliminary in nature, they include Inferred Mineral Resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that these economic assessments will be realized.

The Alto Paraná Project is well supported by current market fundamentals. Chloride slag, the primary product of the Alto Paraná Project, is anticipated to be a key beneficiary of the long-term structural deficit in natural rutile to supply high-grade feedstock to chloride pigment producers. TZMI forecasts demand growth for chloride slag in TiO? pigment end-use markets to show a Compound Annual Growth Rate of 7.7% from 2022 to 2030 (March 2023 Estimate).

In due course, it is expected that additional regional drilling will be completed such that the current resource estimate may be upgraded for the purpose of potentially initiating a Preliminary Feasibility Study.

The technical information in this news release has been reviewed and approved by Colin Rothnie, BSc Hons (Geology), MAusIMM, (201546), employed by UEC as a consulting geologist and a Qualified Person for the TRS, and by TZMI, an independent, third-party consulting firm comprised of industry experts, such as professional metallurgists and professional engineers. TZMI professionals fulfill the requirements to be a "qualified person" for the purposes of S-K 1300.

About Uranium Energy Corp

Uranium Energy Corp. is the fastest growing supplier of the fuel for the green energy transition to a low carbon future. UEC is the largest, diversified North American focused uranium company, advancing the next generation of low-cost, environmentally friendly ISR mining uranium projects in the United States and high-grade conventional projects in Canada. The Company has two production-ready ISR hub and spoke platforms in South Texas and Wyoming. These two production platforms are anchored by fully operational central processing plants and served by seven U.S. ISR uranium projects with all their major permits in place. Additionally, the Company has diversified uranium holdings including: (1) one of the largest physical uranium portfolios of U.S. warehoused U3O8; (2) a major equity stake in Uranium Royalty Corp., the only royalty company in the sector; and (3) a Western Hemisphere pipeline of resource stage uranium projects. The Company's operations are managed by professionals with decades of hands-on experience in the key facets of uranium exploration, development and mining.

Stock Exchange Information:
NYSE American: UEC
Frankfurt Stock Exchange Symbol: U6Z
WKN: AØJDRR
ISN: US916896103

Safe Harbor Statement

Except for the statements of historical fact contained herein, the information presented in this news release constitutes "forward-looking statements" as such term is used in applicable United States and Canadian securities laws. These statements relate to analyses and other information that are based on forecasts of future results, estimates of amounts not yet determinable and assumptions of management. Any other statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects" or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans, "estimates" or "intends", or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved) are not statements of historical fact and should be viewed as "forward-looking statements". Such forward looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Such risks and other factors include, among others, the actual results of exploration activities, variations in the underlying assumptions associated with the estimation or realization of mineral resources, the availability of capital to fund programs and the resulting dilution caused by the raising of capital through the sale of shares, accidents, labor disputes and other risks of the mining industry including, without limitation, those associated with the environment, delays in obtaining governmental approvals, permits or financing or in the completion of development or construction activities, title disputes or claims limitations on insurance coverage. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Many of these factors are beyond the Company's ability to control or predict. There can be no assurance that such statements will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements contained in this news release and in any document referred to in this news release. Important factors that may cause actual results to differ materially and that could impact the Company and the statements contained in this news release can be found in the Company's filings with the Securities and Exchange Commission. For forward-looking statements in this news release, the Company claims the protection of the safe harbor for forward-looking statements contained in the Private Securities Litigation Reform Act of 1995. The Company assumes no obligation to update or supplement any forward-looking statements whether as a result of new information, future events or otherwise. This news release shall not constitute an offer to sell or the solicitation of an offer to buy securities.

View original content to download multimedia:https://www.prnewswire.com/news-releases/uranium-energy-corp-reports-s-k-1300-initial-assessment-and-economic-study-for-the-alto-parana-titanium-project-301985660.html

SOURCE Uranium Energy Corp.



Contact
Uranium Energy Corp. Investor Relations: Toll Free: (866) 748-1030, Fax: (361) 888-5041, E-mail: info@uraniumenergy.com, Twitter: @UraniumEnergy
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Uranium Energy Corp.
Bergbau
A0JDRR
US9168961038
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"