Minera IRL Ltd Announces Definitive Feasibility Study, Ollachea Project, Peru

29.11.2012  |  Marketwired

LONDON, UNITED KINGDOM and TORONTO, ONTARIO -- (Marketwire) -- 11/29/12 -- Minera IRL Limited ("Minera IRL" or the "Company") (TSX: IRL)(AIM: MIRL)(BVL: MIRL), the Latin American gold mining company, is pleased to announce the results of a Definitive Feasibility Study ("DFS") on its Ollachea Project (the "Project"), Peru. The Project is 100% owned by Minera IRL SA subsidiary Minera Kuri Kullu SA ("MKK"). The DFS was carried out by international engineering firm AMEC in conjunction with Coffey Mining, who contributed the resource estimation and underground mining aspects of the study.


Highlights:


Project Economic Indicators



-- Using a gold price of $1,300 per ounce, NPV @ 7% real of $264 million
(pre-tax) and $155 million (post tax); and IRR of 29.2% (pre tax) and
22.1% (post tax)

-- Up-front capital cost estimate of $177.5 million

-- Life-of-mine ("LOM") cash operating cost of $499 per ounce


Project Physical Indicators



-- Canadian National Instrument 43-101 ("NI 43-101") compliant Indicated
Resource of 10.6 million tonnes grading 4.0g/t gold containing 1.4
million ounces gold

-- Probable Mineral Reserve of 9.3 million tonnes grading 3.4g/t gold
containing 1.0 million ounces

-- Rate of 1.1 million tonnes per annum to produce an average of 113,000
ounces gold per year at full capacity

-- Nine year initial mine life including ramp-up and down

-- Underground mining accessed by a 1.2km tunnel currently over 800 metres
advanced

-- Conventional metallurgical processing to extract 91% of the gold


Next Steps



-- Environmental Impact Assessment ("EIA") to be submitted before year-end
thereby initiating permitting

-- Investigating financing and early commencement of detailed engineering

-- Production forecast to commence beginning 2015

-- Upside potential includes the adjacent Concurayoc Zone with a 0.9
million ounces Inferred Resource which is not included in the DFS. The
Minapampa and Concurayoc zones are open ended both along strike and down
dip.


Note: $ denominates United States ("US") dollars unless otherwise stated.


"Ollachea's DFS confirms that Minera IRL has an economically and technically robust, long life project." said Courtney Chamberlain, Executive Chairman of Minera IRL. "Our team of engineers and consultants have done an excellent job on this comprehensive evaluation. This has been bolstered by the practical underground mining experience being obtained from the ongoing exploration drive, which has now advanced over 800 meters. We are confident of a much longer mine life than the initial nine years defined in this study considering that over one million ounces of Inferred Resource has already been identified and that the gold bearing structures are open ended along strike and down dip."


"The EIA will be submitted to the Peruvian authorities shortly thus commencing the permitting process. We are investigating financing options and intend to commence detailed engineering early in 2013. Our target is to start ore processing at the beginning of 2015."


Financial Analysis


The financial analysis was undertaken in constant US dollars, 100% Project, stand alone in country and 100% equity finance basis. It was undertaken at a base case gold price of $1,300/oz. However, the analysis was also performed using a gold price of $1,600/oz to show the impact of a higher gold price. The results of the financial analysis are set out below.



----------------------------------------------------------------------------
Parameter Units Financial Results
-----------------------------------------------
$1,300/oz (base case) $1,600/oz
-----------------------------------------------
Pre-tax Post-tax Pre-tax Post-tax
----------------------------------------------------------------------------
Project cash flow $M 489 325 749 486
----------------------------------------------------------------------------
NPV at 5% real $M 316 194 506 310
----------------------------------------------------------------------------
NPV at 7% real $M 264 155 434 258
----------------------------------------------------------------------------
NPV at 10% real $M 199 108 343 194
----------------------------------------------------------------------------
IRR (real) % 29.2 22.1 40.2 30.2
----------------------------------------------------------------------------
Payback years 3.2 3.7 2.5 3.0
----------------------------------------------------------------------------
Note:
1. NPVs as at commencement of construction
2. NPVs are based on mid-period discounting
3. Before tax is before Special Mining Tax, Workers' Participation Profit of
8% and Income Taxes of 30%
4. Payback starts from the commencement of production
5. The financial results are on 100% Project basis and exclude the agreement
with the community for a 5% participation in MKK on commencement of
production and the Second Additional Payment payable by MKK and due to
Rio Tinto in accordance with Mining Claim Transfer Agreement dated 23
February 2007.
----------------------------------------------------------------------------


Other assumptions included in the financial analysis are:



-- US$: PEN (Peru Sol) of 2.65
-- Third party 1% NSR Royalty
-- Peru Royalty based on an operating margin sliding scale
-- Peru Special Mining Tax based on a operating margin sliding scale
-- Peru Workers' Profit Participation of 8% of pre-tax profits
-- Peru Income tax rate of 30%


Mineral Resources and Mineral Reserves


A NI 43-101 compliant Mineral Resource estimate was announced on 18 July 2012. This Mineral Resource estimate was carried out by consulting firm Coffey Mining Pty Ltd.


The Indicated Mineral Resource estimate over the Minapampa Zone totals 10.6 million tonnes averaging 4.0 g/t gold containing 1.4 million ounces. This resource is contained within six discrete horizons over a strike length of approximately 950 meters and down- dip approximately 350 meters. This estimate was based upon 151 diamond drill holes for 59,509 meters. The mineral resource estimate applies a 2g/t gold bottom cut and top cutting as appropriate for each of the six discrete gold-mineralized horizons that have been defined to date. The dry in-situ bulk density within mineralised zones, based upon 103 bulk density determinations, is 2.83 tonnes per cubic meter.


Included within the Indicated Mineral Resource envelope, the higher grade core Indicated Mineral Resource, using a 3.5g/t gold cut-off, totals 5.1 million tonnes grading 5.3g/t gold containing 0.9 million ounces.


In addition, the Inferred Mineral Resource at Minapampa and Concurayoc, approximately 400 meters west of Minapampa, totals 13.7 million tonnes grading 2.9 g/t gold for 1.2 million ounces. With additional future resource definition drilling, this Inferred Mineral Resource offers potential for a significant mine life extension. The deposit remains open along strike and down dip providing significant future exploration potential.


Probable Mineral Reserves at Minapampa, are shown in the following table. The Probable Mineral Reserves are included within the Indicated Mineral Resources and inclusive of mining dilution.



----------------------------------------------------------------------------
Tonnage Au Grade Contained Au
Category Mt g/t koz
----------------------------------------------------------------------------
Ore (+2g/t Au) 8.7 3.5 983
----------------------------------------------------------------------------
Low Grade Development Ore 0.6 1.5 28
(+1g/t to 2g/t Au)
----------------------------------------------------------------------------
Probable Mineral Reserves 9.3 3.4 1,011
----------------------------------------------------------------------------


The low grade development ore is sourced from development drives that traverse through Indicated Mineral Resource but has been diluted below the Project COG of 2.0g/t Au. As the mining cost for this material will have already been expensed, it is economic to treat through the plant. A mill cut-off grade of 1.0g/t Au has been applied to this material.


Mining & Processing


The mining method will be long-hole open stoping with paste backfill. The main access to the orebody will be via a 1.2 km-long exploration access drive from the plant site in the adjacent valley. This drive is currently in progress and has already advanced over 800 meters. The drive will access the orebody near the lower limit of the drill defined deposit so most ore mining will be from the bottom upwards. Extraction will occur along the orebody strike direction on a retreat basis.


Mine development will continue in parallel with the plant and infrastructure construction. Whilst some ore will be mined and stockpiled during the development period, the actual ore stoping production is scheduled to commence in early 2015, ramping up to the full 1.1 million tonnes per annum rate by mid-2016. Development waste of 2.6Mt will be mined over the LOM.


A comprehensive metallurgical testing programme has been completed in Australia and the United States. This demonstrated good metallurgical response to conventional crush, grind, gravity concentration and carbon-in-leach technology. Gold recovery of 91% is projected.


The processing plant will have a capacity of 1.1 million tonnes per annum. Tailings will be filtered and split between underground cemented fill and dry stacking on surface.


The average steady state (approx. 6.6 years) gold production is approximately 113koz per annum. The following table summarises the mine and processing production.



----------------------------------------------------------------------------
LG Dev. Ore
Ore Mined Mined Ore Processed
--------------------------------------------------
Au Au Total Au Au
Ore grade Ore grade Ore grade Recovery Production
Year (kt) (g/t) (kt) (g/t) (kt) (g/t) (%) (koz)
----------------------------------------------------------------------------
2014 35 3.11 11 1.56 - - - -
----------------------------------------------------------------------------
2015 586 3.46 110 1.51 680 3.21 90.2% 63
----------------------------------------------------------------------------
2016 811 3.07 80 1.53 938 2.91 88.8% 78
----------------------------------------------------------------------------
2017 1,097 3.48 55 1.49 1,117 3.45 90.3% 112
----------------------------------------------------------------------------
2018 1,095 3.66 99 1.44 1,127 3.60 91.2% 119
----------------------------------------------------------------------------
2019 1,099 3.63 87 1.47 1,120 3.59 91.2% 118
----------------------------------------------------------------------------
2020 1,106 3.81 132 1.51 1,132 3.76 92.0% 126
----------------------------------------------------------------------------
2021 1,099 3.58 16 1.50 1,137 3.51 91.5% 118
----------------------------------------------------------------------------
2022 862 3.25 - - 1,128 2.83 91.1% 94
----------------------------------------------------------------------------
2023 738 3.50 - - 738 3.50 91.8% 76
----------------------------------------------------------------------------
2024 203 2.90 - - 203 2.90 93.1% 18
----------------------------------------------------------------------------
Total 8,730 3.50 590 1.49 9,320 3.38 91.0% 921
----------------------------------------------------------------------------


Taking into account the potential to convert the Inferred Mineral Resource at the nearby Concurayoc Zone to the Measured and Indicated categories, as well as the exploration upside, the Company considers that there is an excellent opportunity to extend the full 1.1 million tonnes per annum mining and treatment rate well beyond 2022.


Infrastructure


Ollachea is well served by existing infrastructure and sits astride the new Southern Interoceanic Highway. A high tension power line passes over the project site and a long term contract has been signed with the hydroelectric supplier. There is an abundant source of water and a significant portion of the workforce will be recruited from the local community.


A permanent camp will be developed close to the plant site to accommodate 200 employees.


Capital Cost Estimate


Project development capital cost is estimated to be $177.5 million with an additional LOM sustaining capital of $41.6 million and $4.2 million for closure capital. Capital costs are summarised in the following table.



----------------------------------------------------------------------------
Item Cost
$M
----------------------------------------------------------------------------
Project Capital
----------------------------------------------------------------------------
Mining 55.4
----------------------------------------------------------------------------
Site Development 3.9
----------------------------------------------------------------------------
Process Plant 58.4
----------------------------------------------------------------------------
Ancillary Buildings 3.9
----------------------------------------------------------------------------
Tailings System 5.7
----------------------------------------------------------------------------
Indirect and Owners Cost 31.4
----------------------------------------------------------------------------
Contingency 19.0
----------------------------------------------------------------------------
Total Project Capital 177.5
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Sustaining Capital 41.6
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Closure Costs (net) - End of LOM 4.2
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Total LOM Capital Cost 223.3
----------------------------------------------------------------------------
Note:
----------------------------------------------------------------------------
1. Costs are in 3Q 2012 $.
----------------------------------------------------------------------------


Operating Cost Estimate


Operating costs to mine and treat at a steady state production rate of 1.1 million tonnes per annum were derived from first principles. The LOM average unit operating costs are summarised in the following table.



----------------------------------------------------------------------------
Item $/t ore $/oz
----------------------------------------------------------------------------
Mining 23.4 237
----------------------------------------------------------------------------
Processing 21.5 218
----------------------------------------------------------------------------
G&A 4.3 44
----------------------------------------------------------------------------
Total operating 49.2 499
costs
----------------------------------------------------------------------------
Note:
1. Costs are in 3Q 2012 $.
2. Operating cash costs exclude costs for freight and refining dore, and
royalties.
----------------------------------------------------------------------------


Environmental & Permitting


Environmental baseline information has been collected over approximately a three year period. This is being used in conjunction with special studies, such as hydrogeology and geotechnical, and DFS design details to produce an EIA which is currently in progress and is expected to be submitted by the end of 2012. The submission of the EIA to the Peruvian government authorities will be the basis for the development permitting process.


Community Relations


MKK has developed excellent relationships with the local community and has a 30 year development and operating permit in place. The community will become a 5% equity participant in MKK upon the commencement of production. A significant portion of the workforce will be local people who will be trained and employed at the operation.


Archaeological clearance has been granted for most of the required plant, tailings and infrastructure locations. Remaining clearance is in progress but no sites of national significance have been identified within the area of planned use.


Project Schedule and Moving Forward


The successful completion of the DFS establishes the basis for moving quickly towards development. The excellent progress on the exploration drive will provide the opportunity for uninterrupted progression toward establishing underground infrastructure and development. The EIA will be completed and submitted in a timely manner. Investigations into project financing will now be accelerated.


The project schedule is predicated upon a rapid move toward development. An engineering company will shortly be appointed to commence detailed design and identify long lead items for placement of early orders. Plant and infrastructure construction is scheduled for completion late in 2014 with first feed to the plant at the beginning of 2015. Canadian National Instrument 43-101 compliant report will be filed within the ensuing required 45 day period.


Competent Persons Statement


The preparation of the technical information contained herein was supervised by Courtney Chamberlain, Executive Chairman, BSc and MSc Metallurgical Engineering, a Fellow of the Australian Institute of Mining and Metallurgy (FAusIMM), who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release. Also by Donald McIver, VP Exploration of the Company, MSc Exploration and Economic Geology, a Fellow of the Australian Institute of Mining and Metallurgy (FAusIMM), as well as the Society of Economic Geologists (FSEG), who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the resource information in this press release.


The preparation of the Probable Mineral Reserve contained herein was supervised by John Hearne, FAusIMM, of Coffey Mining, who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release.


The preparation of the Indicated Mineral Resources contained herein was estimated by Doug Corley, Member of the Australasian Institute of Geoscientists (MAIG), and Registered Professional Geoscientist (RP Geo), of Coffey Mining, who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release.


Conference Call


Following the release, Minera IRL plans to host a conference call at 10:00 am Toronto (EDT), 3:00 pm UK (BST), 10:00 am Lima (PET) on November 29, 2012. To participate in the call please dial:



Toll Free (North America): 877-240-9772
Local Toronto and International: 416-340-8527
Global: 800-2787-2090


A live webcast and archive will be available at: http://www.gowebcasting.com/4028


REPLAY:



Dial-in numbers: 905-694-9451 / 800-408-3053/ 800-3366-3052
The replay is available till December 6th, 2012
Passcode: 5695777


To view the images associated with this release, please visit the following link: http://media3.marketwire.com/docs/miner11.pdf


Minera IRL Limited is the AIM traded, TSX and BVL listed holding company of precious metals mining and exploration companies focused in Latin America. Minera IRL is led by an experienced senior management team with extensive industry experience, particularly operating in South America. The Group operates the Corihuarmi Gold Mine and the advanced gold projects Ollachea in Peru and Don Nicolas in Argentina. For more information, please visit www.minera-irl.com.


Some of the statements contained in this release are forward-looking statements, such as estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties.


While these forward-looking statements, and any assumptions upon which they are based, are made in good faith and reflect our current judgment regarding the direction of our business, actual results will almost always vary, sometimes materially, from any estimates, predictions, projections, assumptions or other future performance suggestions herein. Except as required by applicable law or regulation, Minera IRL Limited does not intend to update any forward-looking statements to conform these statements to actual results.


Quality Assurance and Quality Control Procedures Disclosure


The Company has implemented and maintains a Minera IRL quality assurance/quality control (QA/QC) protocol on the Ollachea Project to ensure best industry practice in sampling and analysis of exploration and resource drill core samples. The insertion of field duplicates, certified standards and blank samples into the sample stream form part of the MIRL procedure (these act as an independent check on contamination, precision and accuracy in the analytical laboratory).


Assay results are reported once rigorous QAQC procedures have been approved.


Independent Audit Programmes


Towards maintaining compliancy with international standards as they pertain to the minerals industry resource evaluation and estimation procedure, MIRL regularly contracts the services of industry experts to conduct detailed audits of established QAQC procedures.


The Toronto Stock Exchange neither approves nor disapproves the information contained in this News Release.

Contacts:

Minera IRL

Trish Kent

Vice President, Corporate Relations

+511 418 1230


Canaccord Genuity Limited

(Nominated Adviser & Broker, London)

Adam Miller

+ 44 (0)20 7523 8350


finnCap (Co-broker, London)

Geoff Nash (Corporate Finance)

Matthew Robinson (Corporate Finance)

Joanna Weaving (Corporate Broking)

+ 44 (0)20 7600 1658


RBC Europe Ltd (Co-broker, London)

Stephen Foss

Martin Eales

+44 (0)20 7653 4000


Buchanan (Financial PR, London)

Bobby Morse

Gordon Poole

Louise Mason

+44 (0)20 7466 5000


Hill+Knowlton Strategies (PR, Toronto)

Rick Harari

+1 416 413 4766


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Minera IRL Ltd.
Bergbau
A0MP6A
JE00B1HNYF12
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"