Suche
 
Folgen Sie uns auf:

Northland Resources Operational Update-September 2012

25.09.2012  |  Marketwired

LUXEMBOURG, LUXEMBOURG -- (Marketwire) -- 09/25/12 -- Northland Resources S.A. (TSX: NAU)(FRANKFURT: NPK)(OSLO: NAUR) ("Northland" or the "Company") announces its fourth bi-monthly operational and construction update on the Kaunisvaara project. During this period, July 1-September 21, among other important milestones, Northland fulfilled its second Cost-to-Complete test and has now executed its second drawdown of USD 90 million from the bond facility.



-- The schedule for the Kaunisvaara project remains unchanged, with
production at the Tapuli Mine scheduled to commence in November 2012,
with shipments of concentrate starting in first quarter 2013.
-- The first Kaunisvaara process line was 91% complete and remains on
schedule.
-- The independent engineer, Royal HaskoningDHV (formerly named Turgis),
has confirmed the second Cost-to-Complete test, and the report was
approved by the Trustee, Norsk Tillitsmann. A second drawdown from the
bond agreement of USD 90 million was executed September 21, 2012.
-- The Swedish government will finance further improvements to the
Malmbanan railway as well as to the public road between Kaunisvaara and
Svappavaara.
-- Northland has been granted all four requested slots on the Malmbanan
railway, starting December 8, 2012.
-- First blasting of 400,000 tonnes waste rock at the Tapuli mine was
successfully completed on September 21, 2012.
-- The Company plans to increase production volume to 1.4 dmt(1) in 2013
and to reach the production capacity of 4.0 dmtpa(2) in the third
quarter of 2014, one quarter earlier than previously expected.


THE MINE

-- Approximately 3,697,000 m3 of the Tapuli overburden has been removed.
The current average rate is more than 100,000 m3 per week. Pre-stripping
of the Tapuli central part is close to completion.
-- The first Kaunisvaara process line is 91% complete and remains on
schedule. The second Kaunisvaara process line is 52% complete.
-- The Sahavaara mine and related investments are 32% complete.
-- Power feed cables from substation into electrical rooms have been
installed.
-- Mechanical completion for the Tapuli Line is on track.
-- Construction of the substation is near completion and installation is
progressing according to plan.
-- The following mobile mining equipment has been delivered from Pon-Cat:
-- 1 wheel loader, model 994
-- 2 trucks, model 793F
-- 1 dozer, model D10T
-- 1 grader, model 16M
-- Start-up and performance tests for the Caterpillar equipment as well as
the two SmartROC D65 LF drill rigs from Atlas Copco were completed, and
they are now in use.


THE LOGISTICS CHAIN

-- The build-out of the logistics chain is on schedule for the commencement
of deliveries to customers in the first quarter of 2013.
-- The Swedish government has announced its intention to invest in improved
infrastructure in the County of Norrbotten:
-- SEK 800 million will be allocated to improve the Malmbanan railway,
in addition to the SEK 500 million approved last year.
-- SEK 1.3 billion will be allocated to improve the public road between
Kaunisvaara and Svappavaara where the Northland iron ore concentrate
will be transported by truck.
-- Peab subsidiary, Swerock/Cliffton, has entered into an agreement with
one of the world's leading manufacturers of trucks, Scania, for the
purchase of 400 truck-and-trailer combinations and services during a
nine-year period. The truck-trailer combinations will be optimized for a
gross weight of up to 90 tonnes.
-- Swerock/Cliffton has tested a rig weighing the maximum 90 tonnes to
confirm and optimize future transportation. The results have been very
positive.
-- Four train slots were granted on Malmbanan, starting December 8, 2012.
This gives Northland sufficient capacity to transport 4 million tonnes
per year of high-grade concentrate.
-- The improved roads are expected to be ready for trucking in early 2013.


Pitkajarvi trans-loading terminal:

-- Construction work at the terminal is progressing well and according to
plan.
-- Road and rail interchange work is on schedule.
-- 95% of railway tracks including the switches are in place. The ballast
for the railtracks is 95% complete.
-- Anchor bolts, power lines and electrification are operational.
-- Manufacturing of the rail cars by Kiruna wagon is ongoing and as
contracted.


The Port

-- Construction of the Fagernes Terminal in the Port of Narvik remains on
schedule to handle the first shipment in 2013.
-- Jetty civil works are progressing according to plan.
-- Storage and de-icing facilities are progressing according to plan: land
works have commenced with 70% of excavation work completed.
-- On September 21, Norwegian Rail Administration ("NRA") and Northland
signed an agreement which will ensure that NRA will do the necessary
improvements of the rail connection to Fagernes port from Narvik station
and necessary works on the rail in Fagernes.


Financing


Independent engineer Royal HaskoningDHV ("Royal Haskoning", formerly named Turgis) as well as the bond holder trustee, Norsk Tillitsmann ASA ("Norsk Tillitsmann"), have confirmed Northland's fulfillment of its second Cost-to-Complete test. Consequently, Northland was able to execute the second drawdown of about USD 90 million from its USD 350 million bond loan facility on September 21.


The Company now has sufficient funds to start production at the Kaunisvaara project and thereby generate revenues during the first quarter of 2013. This is due to the bond drawdown; leases nearing completion; and the Cost Overrun Facility provided by Standard Bank.


Northland's Capex to reach full production (4.0 million dmtpa) is expected to increase to USD 956 million (previously USD 875m). The new Capex is 9% above the prediction in the capital raising completed February 2012 due to increased civils and engineering work and buildings costs (including upgrades), as well as tires for mobile equipment and increased costs for rail upgrading. The cost of rail cars is now also included in the new Capex, which they were not in February, 2012. Northland's intention is to sign a lease/rental agreement for the rail cars and storages, which would further reduce Capex.


The Kaunisvaara Project


Site works are progressing well in Kaunisvaara. Mechanical completion for the Tapuli Line is on-track. Primary crusher for the Tapuli mine is in place. Gear units and Cyclopacs of the VertiMills are installed.


Steel installations are completed for the Tapuli stockpile, roofing and installations are ongoing. In the Process Plant building, only electrical installations are still ongoing for the first process line.


Inner walls and flooring are completed for the truck workshop, internal installations are still ongoing. The workshop is sufficiently complete for Pon-Cat when access is required.


Pipeline from Muonio River has been pressurized and the pump station is working. Tailings pipe-line is ready to receive water and water has been successfully pumped into the clearing pond basin.


Conveyor belt is being installed. Substation works are progressing to plan with the transformers and other major equipment having been delivered on time.


Vattenfall is slightly ahead of program for the power supply lines. A power line from last pole in Kaunisvaara to the incoming portal in the substation has been installed.


Health & Safety


Lost Time Injury Frequency Rate ("LTIFR") according to the Swedish standard(3) from the start of the project until end of August 2012 was 5.34 (6.39 for the previous period that ended June 30).


The corresponding number according the international standard(4) for the same period was 0.89 per 200,000 worked hours (previous period: 1.06).


There was one LTIFR incident reported for both the International and Swedish standards during this period, July 1-August 31 (previous two-month period: one).


A total of 49 Near Hits were reported for the same period (previous two-month period: 54).


Northland Resources took over the site safety coordination on April 1, 2012. The operations staff are preparing for takeover from the project organization during third quarter of 2012. A safety coordinator was recruited in June.


Pellivuoma


Pellivuoma is located approximately 15 km west of Sahavaara. The Company controls 100% of the exploration permit, which totals 11,346 hectares. The deposit constitutes potentially significant additional tonnage in the Kaunisvaara area.


Following a review of the ongoing definitive feasibility study ("DFS") work at Pellivuoma in early 2012, management modified the scope of the DFS to ensure that Pellivuoma is developed in the most cost, output and financially-rewarding manner with the Kaunisvaara mining and processing site. Potential scenarios include an increase in the production of high-grade concentrate or an extension of the life of the Kaunisvaara operation in combination with an increase of the production. The DFS is expected to be completed in the beginning of 2013.


Next Operational Update


The Operational Update for the period up to October/November 2012 will be published on November 21, 2012.


Financial Statements and MD&A for the third quarter 2012


The Company will publish its Financial Statements and Management's Discussion and Analysis for the period ending September 31, 2012, on November 14, 2012.


Photos and video clips are available on Northland Resources' website, www.northland.eu.


Karl-Axel Waplan, President & CEO, Northland Resources S.A.


Northland Resources a near-production stage mining company with a portfolio of iron ore projects in northern Sweden and Finland. The Company's Kaunisvaara Project will initially exploit two magnetite iron ore deposits in Sweden. The process will yield a high-grade, high-quality magnetite iron concentrate. The construction of the Kaunisvaara project in Sweden is well underway and mining is planned to start in the fourth quarter of 2012. Northland Resources has entered into off-take contracts for the entire production from Kaunisvaara. The Company is also preparing a Definitive Feasibility Study ("DFS") for its Hannukainen Iron Oxide Copper Gold ("IOCG") Project in Kolari, northern Finland and for its Pellivuoma deposit 15 km from the Kaunisvaara process plant.


Important Notice


Forward-Looking Statements


This announcement may include "forward-looking" statements within the meaning of applicable securities laws. These forward-looking statements can be identified by the use of forward-looking terminology, including the terms "believes", "estimates", "anticipates", "expects", "intends", "may", "will" or "should" or, in each case, their negative, or other variations or comparable terminology. These forward-looking statements include all matters that are expectations concerning, among other things, Northland Resources results of operations, financial condition, liquidity, prospects, growth, strategies and the industry in which it operates. By their nature, forward-looking statements involve risks and uncertainties because they relate to events and depend on circumstances that may or may not occur in the future. Readers are cautioned that forward-looking statements are not guarantees of future performance and that Northland Resources' actual results of operations, financial condition and liquidity, and the development of the industry in which it operates may differ materially from those made in or suggested by the forward-looking statements contained in this press release. In addition, even if Northland Resources' results of operations, financial condition and liquidity, and the development of the industry in which Northland Resources operates are consistent with the forward-looking statements contained in this press release, those results or developments may not be indicative of results or developments in subsequent periods.


(1) Dry million tonnes


(2) Dry million tonnes per annum


(3) Lost Time Injury Swedish standard as adopted by SveMin members: Absence of one shift or more from regular duty following the accident. Reference period: 1 million worked hours.


(4) International Lost Time Injury definition: Absence of three shifts or more from regular duty following the accident. Reference period: 200,000 worked hours.

Contacts:

Northland Resources S.A.

Karl-Axel Waplan

President and CEO

+46 705 104 239


Northland Resources S.A.

Peder Zetterberg

Acting CFO

+46 708 652 120


Northland Resources S.A.

Anders Antonsson

Vice President - Investor Relations

+46 709 994 970


Northland Resources S.A.

Marguerite Manshreck-Head

Investors Relations, Canada

+1 647 224 7882
www.northland.eu


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!




Mineninfo
Northland Resources SE
Bergbau
-
-
Minenprofile
Alle Angaben ohne Gewähr! Copyright © by GoldSeiten.de 1999-2024.
Die Reproduktion, Modifikation oder Verwendung der Inhalte ganz oder teilweise ohne schriftliche Genehmigung ist untersagt!

"Wir weisen Sie ausdrücklich auf unser virtuelles Hausrecht hin!"